The invention relates to a baseball sports field structure on a soft soil foundation and a construction method, comprising a turtleback field and a drainage
system. The
terrain of the turtleback field gradually descends from a high place to the surrounding areas, presenting a natural slope. The drainage
system comprises an annular
drainage ditch surrounding the turtleback field, a plurality of blind ditches arranged at intervals in the turtleback field, and a blind
pipe laid in the blind
ditch. The two ends of the blind
pipe are respectively connected to the annular
drainage ditch, and a water-permeable hole is arranged in the lower part of the blind
pipe. The foundation of the turtleback field is a soft soil foundation. An annular
drainage ditch and a blind
ditch are pre-dug on the soft soil foundation to form a
reinforced concrete base. Concrete is poured on the surface of the soft soil foundation, the annular drainage
ditch and the blind ditch to form a
reinforced concrete base. Gravel is filled in the blind ditch until it is flush with the surface of the
reinforced concrete base on both sides of the blind ditch. Permeable
asphalt is poured on the surface of the reinforced concrete base. A high-performance permeable elastic pad is laid on the surface of the permeable
asphalt. An
artificial turf is laid on the surface of the high-performance permeable elastic pad.