Tunneling construction method for shield tunneling machine
A construction method and technology of shield machine, which are applied in earth-moving drilling, mining equipment, tunnels, etc., can solve the problems of time-consuming and laborious construction sites, dirty and messy, etc., and achieve convenient manufacturing and transportation, high safety factor, and simple and fast construction methods. Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0025] Embodiment one: if Figure 1-4 As shown, the present embodiment is a construction method for tunneling of a shield machine belonging to the field of underground engineering, and specifically relates to a working well 1, a tunnel 5 and a shield machine 6 working in the tunnel 5. The construction method is implemented by The following steps are done:
[0026] ① When the front end of the shield machine 6 is close to the sealing door, stop the construction, remove the sealing door 2 arranged on the well wall 3, and lay the base 18 on the ground of the working well 1;
[0027] ② Then use a large crane to set up the cavity 12 with both ends open on the base 18 in the working well 1, and make the cavity 12 close to the well wall 3, in order to ensure the sealing of the cavity 12 and the entrance 8, A sealing gasket 13 is arranged between the cavity 12 and the well wall 3; at the same time, in order to ensure that the shield machine 6 can move coaxially and linearly in the cav...
Embodiment 2
[0031] Embodiment two: if figure 1 , 4 , 5, 6, and 7, this embodiment is a preferred solution of the present invention, and the difference from Embodiment 1 is that the length of the cavity 12 becomes smaller, and the length of the cavity 12 is reduced to 1 / of the length of the shield machine 6 3. Due to the change of the length of the cavity 12, the construction steps have also been greatly changed. The specific steps are as follows:
[0032] ① When the front end of the shield machine 6 is close to the sealing door, stop the construction, remove the sealing door 2 arranged on the well wall 3, and lay the base 18 on the ground of the working well 1;
[0033] ② Then use a large crane to erect the cavity 12 with both ends open on the base 18 in the working well 1, and make the cavity 12 close to the well wall 3, in order to ensure the sealing of the cavity 12 and the entrance 8, A sealing gasket 13 is arranged between the cavity 12 and the well wall 3; at the same time, in or...