A constant resistance anchor beam support method for gob-side roadway roof in integrated production and retention mining

A technology of roadway roof and roadway, applied in ground mining, mining equipment, earthwork drilling and other directions, can solve problems such as restricting the development of the coal industry, waste of resources, non-compliance, etc.

Active Publication Date: 2019-03-22
CHINA NAT COAL GROUP CORP +2
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In order to solve this problem, traditional longwall mining adopts the method of leaving coal pillars between the transportation roadway in the lower section and the air return roadway in the upper section to maintain the stability of the roof of the transportation roadway in the lower section. The working face of the lower section is separated from the goaf of the working face of the upper section. This coal mining method of maintaining the roof of the roadway along the goaf by retaining coal pillars has caused the disadvantages of mining technology such as excavation before mining and separation of excavation in coal mining. , which further lead to high production cost, low production efficiency and waste of resources, and because of the concentration of stress in the surrounding rock of the gob-side roadway, impact dynamic disaster accidents occur
The application rate of this mining method in my country's state-owned large and medium-sized coal mines has reached more than 80%, which has caused problems in my country's coal industry, such as safety, mining costs and waste of resources, restricting the development of my country's coal industry, and does not meet the needs of my country's energy development and transformation in the new era

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A constant resistance anchor beam support method for gob-side roadway roof in integrated production and retention mining
  • A constant resistance anchor beam support method for gob-side roadway roof in integrated production and retention mining
  • A constant resistance anchor beam support method for gob-side roadway roof in integrated production and retention mining

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0040] The research has been successfully tested in the 30104 working face of Nanliang Mine, a subsidiary of China Coal Group. The design production capacity of this mine is 1.20Mt / a, and the geological structure of the mine field is simple and stable. The main coal seams are 2-2 and 3-1 coal seams. The second level 3-1 coal mineable area is about 22.44km2, the coal thickness is 1.47-2.88m, and the average coal thickness is 2.06m, which is recoverable for the near-horizontal whole minefield. The average buried depth is 117.45m, the industrial reserves are 79.09Mt, and the recoverable reserves are 54.42Mt. The 301 panel is located on the east and west wings of 3-1 Coal Central Avenue, which is a double-wing panel. The first mining face (30102 face) is located in the southeast of the 301 panel. It is arranged in the east-west direction and advances towards the road. The 30104 test working face is located in the east wing of the 301 panel area, and it is the test working face f...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a mining and remaining integration exploitation entry-along-goaf roof constant-resistance anchor beam support method which comprises the following steps: (1) delimiting a mining and remaining exploitation region, tunneling the mining and remaining region to form a mining and remaining region boundary guide roadway and an exploitation working face which are perpendicularly arranged, and carrying out deep hole presplitting in an exploitation direction to form a roof-cut presplit crushed zone; (2) mounting a working face hydraulic bracket, a coal cutter, a conveyor and a kerf-beside-roadway hydraulic bracket on the exploitation working face; (3) cutting an entry-along-goaf by using the coal cutter, and conveying coal bodies through the telescopic scraper blade conveyer; (4) supporting the entry-along-goaf by using an end socket hydraulic bracket and a beside-roadway roof-cut hydraulic bracket, reinforcing an immediate roof by using a constant-resistance anchor cable, and tightly hanging the immediate roof to a main roof; (5) with exploitation, enabling the immediate roof of a goaf to slide off along the roof-cut presplit crushed zone to enable a resistance anchor beam with high constant resistance to be located in a stope side distressed zone and anchored on the main roof; (6) after the entry-along-goaf is stabilized, removing the end socket hydraulic bracket and the beside-roadway roof-cut hydraulic bracket in the entry-along-goaf.

Description

technical field [0001] The invention relates to a constant-resistance anchor beam support method for the roof of gob-side roadway in integrated mining and retention mining. The edge of the gob is reinforced with the roof of the gob-side roadway cut by a coal cutter. Background technique [0002] For a long time, my country's coal production has been dominated by longwall mining, that is, the mining area is divided into several sections, and each section is first dug up and down along the tunnel as a ventilation and transportation roadway. After the upper section is recovered, the lower section is transported. The roadway is located at the edge of the goaf after mining in the upper section of the working face. Due to the side support pressure of the stope and the repeated disturbance of the mining dynamic pressure, the roof pressure of the transportation roadway in the lower section is high, and the surrounding rock deformation of the roadway is large. In order to solve this ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21C41/18E21D20/00E21D15/44
CPCE21C41/18E21D15/44E21D20/00
Inventor 祁和刚蔡峰宫守才郑忠友朱磊杨晓科刘成勇李学强刘文涛
Owner CHINA NAT COAL GROUP CORP
Features
  • R&D
  • Intellectual Property
  • Life Sciences
  • Materials
  • Tech Scout
Why Patsnap Eureka
  • Unparalleled Data Quality
  • Higher Quality Content
  • 60% Fewer Hallucinations
Social media
Patsnap Eureka Blog
Learn More