Business line tunnel and bridge section concrete tie renewal method
A technology for concrete and sleepers, which is applied in the field of replacement of concrete sleepers in business line tunnels and bridge sections. It can solve problems such as failure to meet operational requirements, and achieve the effect of improving sleeper replacement efficiency and improving replacement efficiency.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] A method for replacing concrete sleepers in a tunnel section of a business line provided in this embodiment includes:
[0041] To unload the sleeper, unload the sleeper 4 to the ditch on both sides of the first section of the roadbed at both ends of the tunnel in advance, arrange it neatly and anchor it;
[0042] For construction preparation, first determine the position of "opening the door", remove or remove the anti-climbing equipment and gauge rods that affect the operation, and mark the rail waist of track 3 with paint according to the designed sleeper position. Sprinkle water on the ballast bed in the replacement section, and install temporary lighting equipment at the same time. According to the compaction or dirtiness of the ballast bed in the replacement section, replenish the ballast 2 with a ballast repair vehicle;
[0043] Reverse the sleepers, and use a flatbed car or a monorail trolley to transport the new sleepers into the tunnel. The 4 sleepers are stack...
Embodiment 2
[0066] A method for replacing concrete sleepers in the bridge section of the business line provided in this embodiment includes:
[0067] Before changing pillows, manually remove the guard rails on the bridge by using the pillow changing skylight point, and push the inside point to the roadbed on both sides of the line outside the bridge head with a flatbed truck, outside the safety limit.
[0068] The beam body is strengthened, and the anchorage strength, corrosion degree and damage degree of the steel bracket U-bolt are inspected on site, and corresponding marks are made. To check the transverse connection of concrete beams, and to consider whether the increase of eccentric load on the beam body will affect its stability, it is necessary to have the investigation and experiment results of relevant units, and take corresponding reinforcement measures.
[0069] Among them, it is forbidden to stack sleepers and bridge sleepers on the sidewalk, and bridge sleepers must be placed...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com