Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Electric power engineering project site quality acceptance management method and system

A technology of electric power engineering and projects, applied in the field of project acceptance, can solve the problems of weak system implementation, easy alteration, non-destructive, etc., and achieve the effect of improving satisfaction, improving efficiency, and reducing costs

Inactive Publication Date: 2019-02-12
FOSHAN POWER SUPPLY BUREAU GUANGDONG POWER GRID
View PDF5 Cites 14 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] On-site management of power enterprise infrastructure involves multiple units, including employees within the power enterprise system and personnel from cooperative units. On-site quality inspection of infrastructure is the most important thing related to quality and safety, but on-site quality inspection of infrastructure and on-site personnel There are deficiencies in the management and control of power grid projects, mainly reflected in the construction of power grid infrastructure projects. On-site operators carry paper forms for on-site data collection. After completing the form data filling, they must return to the office for centralized reporting of form data or upload attachments. , There are many disadvantages in such an operation method, mainly including: the participating units have weak safety awareness and poor system implementation; on-site operations have become desk operations, and there is a phenomenon of "two skins", and the operators fill in the form data are basically memoirs; The inspection records are paper-based and filled in manually, which are prone to alteration and non-destructive situations.
On-site safety and quality control involve many standards, regulations, procedures, and specifications, which cannot be queried and referenced on the job site
The basic knowledge and basic skills of on-site personnel are weak, and the system implementation is not accurately grasped

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Electric power engineering project site quality acceptance management method and system
  • Electric power engineering project site quality acceptance management method and system
  • Electric power engineering project site quality acceptance management method and system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0035] An embodiment of the present invention provides a method for on-site quality acceptance management of electric power engineering projects, see figure 1 , the method can include:

[0036] Step S11 , the on-site acceptance personnel use mobile terminals preset with uniform quality acceptance and evaluation standards to collect on-site quality data of the items to be accepted, and perform acceptance evaluation on the items to be accepted.

[0037] In this embodiment, through the application of the power infrastructure inspection and evaluation link, the original on-site manual form filling is changed to the on-site operation on the mobile terminal, which eliminates the mistakes of filling in from memory after the event, and there will be no record alteration or damage. There are many standards, rules, regulations, and norms involved in on-site safety and quality control, which can be directly queried and referenced through mobile terminals on the job site. The form data a...

Embodiment 2

[0044] An embodiment of the present invention provides a method for on-site quality acceptance management of electric power engineering projects, see figure 2 , the method can include:

[0045] In step S21, the construction unit prepares the quality acceptance and evaluation standards for the sub-projects and sub-projects in the construction process of the project according to the project progress plan and the sub-project structure of the WBS for review and use by the project acceptance unit.

[0046] In this embodiment, before the start of the project, the construction unit prepares the quality acceptance standards and quality acceptance evaluation forms for the construction process divisions and sub-projects according to the sub-sections and sub-project structures of the WBS according to the project schedule. After confirming that it is correct, report to the supervisory unit and the owner's project department for review. It can include new acceptance evaluation division, ...

Embodiment 3

[0063] An embodiment of the present invention provides an on-site quality acceptance management system for electric power engineering projects, which realizes the method described in Embodiment 1 or 2, see image 3 , the system may include: a mobile terminal 100 , a background server 200 , and an audit terminal 300 .

[0064] The mobile terminal 100 (for example: a tablet computer, a smart phone, etc.) is preset with unified quality acceptance and evaluation standards, and is used for on-site inspection personnel to collect on-site quality data of items to be inspected and conduct acceptance evaluation on the items to be inspected.

[0065] In this embodiment, specifically, the quality acceptance and evaluation standards can be prepared by the construction unit according to the project schedule and the subdivision and sub-item project structure of the WBS, and reviewed and used by the project acceptance unit.

[0066] In this embodiment, before the start of the project, the co...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method and a system for site quality acceptance management of an electric power engineering project. The method comprises the following steps: a site acceptance personnel collects site quality data of items to be accepted by using a mobile terminal preset with a unified quality acceptance and evaluation standard, and performs acceptance evaluation on the items to be accepted; Transfer the collected site quality data and the corresponding evaluation results to the background server for the project quality inspection person in charge to check the implementation of acceptance work and feedback the acceptance work problems and the corresponding project rectification opinions; The on-site acceptance personnel shall, according to the received feedback acceptance work problems and the corresponding project rectification opinions, request the items to be accepted to make corresponding rectification, and feedback the rectification situation of the items to be acceptedby the mobile terminal. The invention realizes the on-site operation truly through the on-site operation of the mobile terminal, eliminates the phenomenon of 'two skins', makes the on-site operation control of the capital construction in place, executes each link according to the standard, and ensures the safe and high-quality construction of the engineering project.

Description

technical field [0001] The invention relates to the technical field of project acceptance, in particular to a method and system for on-site quality acceptance management of electric power engineering projects. Background technique [0002] On-site management of power enterprise infrastructure involves multiple units, including employees within the power enterprise system and personnel from cooperative units. On-site quality inspection of infrastructure is the most important thing related to quality and safety, but on-site quality inspection of infrastructure and on-site personnel There are deficiencies in the management and control of power grid projects, mainly reflected in the construction of power grid infrastructure projects. On-site operators carry paper forms for on-site data collection. After completing the form data filling, they must return to the office for centralized reporting of form data or upload attachments. , There are many disadvantages in such an operation...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/10G06Q50/06
CPCG06Q10/103G06Q50/06
Inventor 肖招娣皇甫汉聪宋宇杨飞邢迪余永忠王永才庞维欣丁剑波
Owner FOSHAN POWER SUPPLY BUREAU GUANGDONG POWER GRID
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products