Design method of deeply-buried PBA subway station section

A technology of cross-section design and subway station, applied in underground chambers, mining equipment, earth-moving drilling, etc., it can solve the problems of reducing land subsidence, complex surrounding environment, and difficulty in ensuring safety, so as to reduce the impact of noise and vibration, The construction work environment is good and the quality control is guaranteed.

Active Publication Date: 2019-12-13
BEIJING NO 4 MUNICIPAL CONSTR ENG +1
View PDF9 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, these methods have different defects and limitations for construction environments with complex surrounding environments, dense underground pipelines, poor geological conditions, abundant groundwater, and large cross-sectional spans.
[0003] 1. For the working conditions with a lot of ground traffic and underground pipelines, the open-cut method must carry out pipeline relocation and traffic evacuation during construction, so the construction is disturbed and the construction period is long; in addition, the temporary relocation of pipelines and the cost of land occupation high, poor economy
[0004] 2. The shallow-buried double-side-wall pilot pit method adopted is extremely unfavorable for the safety control of the pipeline above the structure and the surrounding environment for the construction environment with poor geological conditions, complex surrounding environment, and many underground pipelines, and the construction risk is high. It is difficult to guarantee safety from theoretical analysis
[0006] However, due to its wide application range, the PBA method is suitable for excavation of tunnels with poor strata, poor geological conditions, large spans, and strict ground subsidence requirements, and can reduce ground subsidence and remove temporary support with relatively small workload, simplifying The construction technology and work efficiency are relatively high, so it is applied in the construction of long-span subway stations, but it has not been applied to the construction of deep-buried tunnels
Moreover, it increases the floor area required for construction, increases the workload of demolition and modification and the initial investment, and at the same time brings many uncertain factors in the construction period.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Design method of deeply-buried PBA subway station section
  • Design method of deeply-buried PBA subway station section

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0038] see figure 1 , the construction of a subway station in the central area of ​​a certain northern city. The construction of the subway station runs through the existing city center bridge, and the subway station is symmetrically located on both sides of the bridge. The bridge is equipped with prefabricated concrete retaining walls on both sides of the high fill of the road. Those with a fill height of less than 3m are cantilevered; Set up a settlement joint (expansion joint) at intervals of 2-28m (at the junction of the foundation staggered abutment and the retaining wall and the abutment), the width of the joint is 2cm, and the joint is filled with asphalt and hemp. Linoleum waterproof layer, foundation, ground burden, anti-collision guardrail expansion joints and settlement joints are all consistent with the board joints; the distance between the drain holes is 4m, and they are located at the board joints, and the drain holes are 30cm above the ground line and adopt ga...

Embodiment 2

[0058] A method for designing a section of a subway station using a deeply buried PBA, comprising the following steps:

[0059] a. Detect the ground cavity above the section structure of the station;

[0060] b. Arrange ground dewatering wells and horizontal wells in the cave, and set composite anchor piles 14 on the ground;

[0061] c. Build a large pipe shed 4 at the position above the main arch 1 and the small pilot holes 2 and 3, and carry out deep hole grouting to reinforce the soil;

[0062] d. Construct small pilot tunnels 2 and 3 and pre-embed connecting steel bars;

[0063] e. Erect the grid arches of the small pilot holes 2 and 3, and connect them with the pre-embedded connecting steel bars;

[0064] f. Perform initial support in the small pilot holes 2 and 3, and then install side piles 5 and 6 in the small pilot holes 2 and 3 respectively. Concrete backfill, and then form the crown beams 7 and 8 of the side piles 5 and 6 respectively;

[0065] g. Starting from ...

Embodiment 3

[0086] A method for designing a section of a subway station using a deeply buried PBA, comprising the following steps:

[0087] a. Detect the ground cavity above the section structure of the station;

[0088] b. Arrange ground dewatering wells and horizontal wells in the cave, and set composite anchor piles 14 on the ground;

[0089] c. Build a large pipe shed 4 at the position above the main arch 1 and the small pilot holes 2 and 3, and carry out deep hole grouting to reinforce the soil;

[0090] d. Construct small pilot tunnels 2 and 3 and pre-embed connecting steel bars;

[0091] e. Erect the grid arches of the small pilot holes 2 and 3, and connect them with the pre-embedded connecting steel bars;

[0092] f. Perform initial support in the small pilot holes 2 and 3, and then install side piles 5 and 6 in the small pilot holes 2 and 3 respectively. Concrete backfill, and then form the crown beams 7 and 8 of the side piles 5 and 6 respectively;

[0093] g. Starting from ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a design method of a deeply-buried PBA subway station section. The design method includes the following steps that a, a void is detected; b, a composite anchor rod pile (14) is driven on the ground; c, a large pipe shed (4) is applied; d, small pilot tunnels (2 and 3) are constructed; e, grille arch centers for the small pilot tunnels (2 and 3) are erected; f, initial supporting is conducted on the inner parts of the small pilot tunnels (2 and 3), and then side piles (5 and 6) are applied in the small pilot tunnels (2 and 3) correspondingly; g, a main body arch part (1) is excavated, initial supporting is conducted, and a secondary lining structure (9) is poured by concrete; h, a soil mass of a lower main body center (10) is excavated; i, a bottom plate (11), a side wall (12) and a middle plate (13) of a lower secondary lining structure of the lower main body center (10) are constructed; and j, an accessory structure is applied, and a complete station structureis formed. According to the method, the construction safety, the construction quality and the construction period can be ensured, the cost can be saved, and the construction efficiency can be improved; and section structure design is reasonable, the overall structure is stable, construction is easy and convenient, and the use effect is good.

Description

technical field [0001] The invention belongs to the rail transit equipment industry, and relates to the technical field of underground structure engineering construction of urban rail transit vehicles, in particular to a method for designing a section of a deep-buried PBA subway station. Background technique [0002] At present, the construction technology level of large-span tunnels in China mainly includes open-cut method and shallow buried method. Among them, the shallow burial and underground excavation methods include the double-side wall pilot pit method and the "PBA" method used in large-span subway stations. However, these methods have different defects and limitations for construction environments with complex surrounding environments, dense underground pipelines, poor geological conditions, abundant groundwater, and large cross-sectional spans. [0003] 1. For the working conditions with a lot of ground traffic and underground pipelines, the open-cut method must c...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E21D9/14E21D9/00E21D11/15E21D11/18E21D11/10
CPCE21D9/00E21D9/001E21D9/003E21D9/14E21D11/10E21D11/15E21D11/18
Inventor 孔恒迟子利岳爱敏彭明玉史磊磊鲍宇姜兆丰戴建伟周健
Owner BEIJING NO 4 MUNICIPAL CONSTR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products