BIM-based concrete fabricated building construction method

A building construction and assembly technology, which is applied in the direction of construction, building structure, and building materials processing, can solve problems such as construction management difficulties, repeated design revisions, and large impacts, so as to ensure design quality and constructability, The effect of improving construction efficiency and quality

Pending Publication Date: 2020-03-27
中国电建集团江西省水电工程局有限公司
View PDF3 Cites 30 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] At present, the design of concrete prefabricated buildings adopts two-dimensional CAD design, and the independent design of architecture, structure, electromechanical and other disciplines lacks effective and precise coordination and interaction, which easily leads to repeated design revisions, and the problem of professional collaboration in prefabricated buildings is more prominent
[0004] In the construction process of prefabricated concrete buildings, the installation sequence of prefabricated components has a great influence on the on-site construction, and because the prefabricated components need to be connected in wet work after installation, there are many cross operations in the on-site construction, and construction management is difficult

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • BIM-based concrete fabricated building construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020] Embodiments of the present invention are further described below with reference to the accompanying drawings.

[0021] like figure 1 As shown, the BIM-based concrete prefabricated building design and construction method in this embodiment, the method steps are as follows:

[0022] (1) Building overall BIM model creation and drawing review optimization

[0023] According to the overall design drawings of the project, use Revit modeling software to create building and structural models, and create pipeline models for water supply and drainage, fire protection, HVAC, etc., and place strong and weak current point models. In addition, the toilet equipotential and grounding should also be created. In the process of model creation, it should be ensured that the size of the model and the position of the drawing are consistent. Integrate various professional BIM models through Navisworks software, automatically find model collision problems through the collision function, and ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a BIM-based concrete fabricated building construction method, comprising the following steps: creating a building full-professional integral BIM model, optimizing integral design, splitting prefabricated parts, deepening prefabricated part nodes, performing construction simulation optimization design, performing engineering quantity statistics, drawing a prefabricated partprocessing drawing, and manufacturing a prefabricated part two-dimensional code. By creating the visual informationized BIM model, the BIM-based concrete fabricated building construction method improves the collaborative design of information of the building, the structure and the electromechanical specialty, avoids the problems of mistakes, omissions, collisions and lacks of the design specialties, and improves the design quality. Meanwhile, the assembly type construction process is visually simulated through BIM, and the problem optimization design in construction is found in time, and the design and construction barrier is broken through. Besides, the BIM technology can perform rapid drawing according to the model, and the design quality is improved through automatic statistics of the engineering quantity, and visual construction simulation can further guide field construction, and the generated two-dimensional code can be used for information tracing of the prefabricated part, andthe overall construction quality of the prefabricated building is improved.

Description

technical field [0001] The invention belongs to the field of prefabricated buildings, in particular to a BIM-based concrete prefabricated building construction method. Background technique [0002] Prefabricated buildings are buildings assembled on site using prefabricated components. Because of their high degree of industrialization, they can effectively save resources and energy, reduce construction pollution, improve labor productivity and quality and safety, and meet the requirements of green buildings. Prefabricated buildings can be divided into concrete structures, steel structures, and wood structures according to material classification. Prefabricated concrete structures have gradually become the mainstream development direction of domestic prefabricated buildings due to their rich sources of raw materials, low cost, and good thermal insulation performance. application. [0003] At present, the design of concrete prefabricated buildings adopts two-dimensional CAD de...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06F30/13G06F30/20G06T17/00E04G21/14
CPCG06T17/00E04G21/14
Inventor 刘小林王婷陈海涛黄佩兵
Owner 中国电建集团江西省水电工程局有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products