BIM-based construction process planning management method and system
A management method and construction scheme technology, applied in data processing applications, special data processing applications, resources, etc., can solve the problem that the 3D model cannot reflect the construction process, etc., and achieve the effect of improving management and control capabilities and ensuring reasonable planning
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0040] A BIM-based construction process planning management method of the present invention, see figure 1 shown, including the following process:
[0041] Step 1. According to the design documents and design requirements of the engineering project, establish a three-dimensional BIM model of engineering construction, establish a construction process flow model according to the construction technology and construction method, and, according to the requirements of the construction technology and construction method, the established three-dimensional model can be compared with The construction process flow models can correspond to each other; then establish a virtual construction resource model, including construction equipment, construction personnel, formwork and other construction resources. Formwork refers to the materials used in formwork engineering in engineering construction, such as wooden formwork and steel structure formwork .
[0042] Using Dassault 3DE software based...
Embodiment 2
[0061] Based on the same inventive concept of Embodiment 1, a BIM-based construction process planning management system of the present invention includes:
[0062] The model acquisition module is used to acquire the engineering construction BIM three-dimensional model, the construction process flow model and the construction resource model of the engineering project;
[0063] The association distribution module is used to divide the three-dimensional model of the engineering construction BIM according to the sequence of the process in the construction process flow model to obtain a number of corresponding three-dimensional models of engineering components, and use each process and the three-dimensional model of the engineering components completed in the process to use in the construction process Associated allocation of construction resources in the construction resource model;
[0064] The resource allocation verification module is used to export the usage of construction re...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com