Quick adjustment method of jack during four-point jacking construction of bridge
A rapid adjustment, jacking technology, applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0043] The following is a quick adjustment method for jacks that takes into account both the accuracy of the jacking position of the bridge and the balance of the jacking force in the four-point jacking construction of the bridge involved in the present invention in conjunction with the accompanying drawings and specific embodiments.
[0044] Such as Figure 4 As shown, a bridge is lifted symmetrically by four jacks, and the supporting centers of the first to fourth jacks are respectively , , , , the first jack and the fourth jack are a group, placed on the pier at one end of the bridge; the second jack and the third jack are in a group, placed on the pier at the other end of the bridge, and The straight-line distance of , and The straight-line distance of ;A displacement sensor and a pressure sensor are installed on each jack, and the jacking distance and jacking force of each jack are monitored in real time through signal collection and transmission,
[004...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com