A kind of construction method for strengthening and strengthening karst cave of underground pile foundation

A construction method and technology for pile foundations, which are applied in basic structure engineering, chemical instruments and methods, filling and other directions, can solve problems such as geological disasters, damage to piling equipment, casualties, etc., to reduce the strength of mountain piles and ensure stability. , the effect of increasing the amount of grouting
CN109208625BActive Publication Date: 2019-08-30ARCHITECTURAL DESIGN RES INST OF GUANGDONG PROVINCE

Patent Information

Authority / Receiving Office
CN Β· China
Patent Type
Patents(China)
Current Assignee / Owner
ARCHITECTURAL DESIGN RES INST OF GUANGDONG PROVINCE
Publication Date
2019-08-30

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a strengthening and reinforcing mountain piling construction method for an underground pile foundation cavern. The strengthening and reinforcing mountain piling construction method comprises the steps that (1), advanced drilling is conducted, specifically, the cavern situation of a site is displayed according to survey data of a project, advanced drilling is conducted before pile forming, and the advanced drilling depth should be drilled till the cavern situation below the pile bottom is proven; (2), hole forming is conducted, specifically, a pile hole is formed in thedesign elevation of the pile bottom; (3), deep drilling is conducted, specifically, a miniature steel pipe is drilled to the cavern bottom; (4), mountain piling is conducted, specifically, mountain piling comprises dredging, discharging for stacking and filling, grouting for consolidation and re-inspection; and (5), pile forming is conducted, specifically, the miniature steel pipe penetrates through a filler pile to be driven to the cavern bottom, a made steel reinforcement cage is put into the pile hole, pile body concrete is poured into a pile, and construction is completed. According to thestrengthening and reinforcing mountain piling construction method, the harm of the underground pile foundation cavern can be safely, quickly, economically, thoroughly and effectively treated, the construction safety and the pile forming quality of the project pile are guaranteed, and the bearing capacity and anti-deformation requirements of the structure are met.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to a method for treating karst caves, in particular to a construction method for strengthening and reinforcing karst caves for underground pile foundations. Background technique

[0002] With the continuous acceleration of urbanization in our country, the construction of urban infrastructure has been further developed, and the number of high-rise buildings is increasing, which puts forward higher requirements for the quality and safety of pile foundation construction. In the process of pile foundation construction, it is not uncommon to encounter bad geology of karst caves. Since pile foundation construction is an underground concealed project, karst caves bring great difficulties to pile foundation construction. If reasonable treatment is not carried out, there will be the following hazards :

[0003] (1) Collapsed hole: The hole wall is unstable and collapsed, and accidents such as stratum subsidence, damage to pile driving too...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine