An Embankment Treatment Method Combining Load Reduction, Reinforcement and Drainage
A treatment method and embankment technology, applied in the field of traffic engineering, can solve problems such as limited tensile strength, increased embankment load, and hidden dangers of traffic accidents, so as to improve the overall stiffness and deformation resistance, reduce the effect of vertical additional stress, and improve the overall The effect of stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0061] When it is determined that the type of road where the embankment to be processed is located is the construction road type, such as figure 1 Shown, the present invention comprises the steps:
[0062] Step S101: Determine the road section with potential differential settlement, and determine it as the target embankment that needs to be processed;
[0063] Step S102: performing pretreatment on the target embankment to be processed so that its compaction degree meets the preset design requirements;
[0064] Specifically, in this embodiment, the site is leveled according to the design and specification requirements, and then rolled according to the design requirements, so that the degree of compaction should meet the design and specification requirements;
[0065] Step S103: Calculate the replacement rate according to the requirements of controlled settlement, and in this embodiment, the material of the pipeline 2 used is stainless steel. In other embodiments, the material ...
Embodiment 2
[0080] When it is determined that the type of road where the embankment to be processed is located is the type of road open to traffic, such as figure 2 Shown, the present invention comprises the steps:
[0081] Step S201: Determine the entire road as the embankment to be processed as the target embankment to be processed;
[0082] Step S202: performing pretreatment on the target embankment to be processed so that its compaction degree meets the preset design requirements;
[0083] Specifically, in this embodiment, the site is leveled according to the design and specification requirements, and then rolled according to the design requirements, so that the degree of compaction should meet the design and specification requirements;
[0084] Step S203: Calculate the replacement rate according to the requirements of controlled settlement, and in this embodiment, the material of the pipeline 2 used is stainless steel. In other embodiments, the material of the pipeline can also be ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com