Method for preventing upward floating of existing tunnel during unloading of earthworks
A technology for existing tunnels and earthwork, applied in protection devices, buildings, infrastructure projects, etc., can solve problems such as floating of existing tunnels, and achieve the effect of overcoming floating, convenient operation and overall simplicity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] to combine Figure 1-3 , in this embodiment, a method for preventing the existing tunnel from floating up when earthwork is unloaded is provided.
[0031] This embodiment is aimed at removing the soil mound on the surface directly above the tunnel to avoid weathering of the soil mound and raising dust, and at the same time construct other buildings on the surface to beautify the urban environment.
[0032] The method includes the following steps:
[0033] Step 1. Determine the range and depth of earthwork that needs to be unloaded right above the existing tunnel;
[0034] In this embodiment, first confirm the range and depth of the earthwork that needs to be unloaded, and then determine the range and depth of the earthwork that needs to be unloaded directly above the existing tunnel;
[0035] Then go to step 2;
[0036] Step 2. Excavate the soil on both sides of the existing tunnel and at the periphery of the earthwork that needs to be unloaded to the depth determine...
Embodiment 2
[0049] Please refer to Figure 4-6 , the purpose of this embodiment is to excavate the foundation pit from the surface directly above the existing tunnel, and construct the corresponding buildings, that is, the soil with a certain thickness between the surface and the existing tunnel is removed, and then the existing tunnel is constructed. There is a certain amount of unloading in some tunnels. Therefore, in order to prevent the existing tunnels from floating up during the unloading process, this embodiment proceeds according to the following method.
[0050] The method includes the following steps:
[0051] Step 1. Determine the range and depth of earthwork that needs to be unloaded right above the existing tunnel;
[0052] In this embodiment, first confirm the scope and depth of all unloaded earthworks that need to be excavated as a whole, and then determine the scope and depth of the unloaded earthworks that are directly above the existing tunnel in the foundation pit;
...
Embodiment 3
[0068] In this embodiment, the construction object is a combination of the earthwork on the corresponding surface directly above the existing tunnel and the earthwork corresponding to the excavation of the foundation pit directly above the existing tunnel.
[0069] The construction method is the combination of Embodiments 1 and 2, that is, the processed soil is the earthwork corresponding to the earthwork on the surface and the foundation pit, and the rest are the same.
[0070] In Embodiment 1-3, the present invention uses the need to unload the earthwork that is reserved directly above the existing tunnel and can have an impact on the existing tunnel, and then carries out pile construction on both sides of the need to unload the earthwork, and then needs to be unloaded. Unload the bottom of the earthwork for pipe jacking construction, and then construct the top beams connecting the piles on both sides to form bench piles that are pressed directly above the existing tunnel. F...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com