A design method and technology of limit height, applied in bridge construction, bridges, bridge parts, etc., can solve the problems of increasing the limit height and small limit height of the gravity abutment, and achieve the enhancement of the stability of the front wall and the increase of the limit height. , the effect of reducing the scale of construction
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0020] A design method for increasing the limit height of a gravity abutment, which is realized by the following steps:
[0021] Step 1: Measure the transverse width of the gravity abutment; if the transverse width of the gravity abutment is less than the set threshold, use several prestressed anchor cables 1 to connect the two side walls 2 of the gravity abutment to pull together;
[0022] Step 2: Measure the gradient of the transverse bridge of the gravity abutment to the ground line 3; if the gradient of the transverse bridge of the gravity abutment to the ground line 3 is greater than the set threshold, several prestressed anchor cables 1 are used to tie the gravity bridge to the ground line 3. The side wall 2 of the platform is anchored together with the mountain body 4;
[0023] Step 3: Add an unloading platform 6 on the back of the front wall 5 of the gravity abutment.
[0024] In the first step, the set threshold of the width of the transverse bridge of the gravity a...