A method of one-time detonation of large-section tunnels
A detonation method and large-section technology, which can be used in tunnels, blasting, earthwork drilling and mining, etc., can solve the problem of large throwing range of flying stones, and achieve the effect of reducing the peak value of vibration
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0041] A one-time blasting method for large-section tunnels, which is suitable for the drilling and blasting construction of large-section tunnels in mines, especially under the condition of using an integrated drilling, loading, and transporting tunneling machine. The steps include:
[0042] S1. Divide the excavation section into upper steps and lower steps, and the upper steps are arranged ahead of the lower steps; the distance between the upper steps and the lower steps is greater than the length of the excavation cycle.
[0043] S2. Peripheral holes are arranged along the excavation contour of the upper step, and explosives are installed in the peripheral holes.
[0044] S3. Arrange multiple hole vertical lines evenly along the vertical direction on the upper step, and arrange multiple hole horizontal lines on the upper step parallel to the tunnel floor to determine the hole base point; the intersection between the hole vertical line and the hole horizontal line is the hole...
Embodiment 2
[0056] combine Figure 1 to Figure 3 A method for detonating a large-section tunnel at one time is described in detail, and the specific steps may further include:
[0057] S1. Divide the excavation section A into upper steps A 1 and down step A 2 Two steps, go up step A 1 Advance down step A 2 A certain distance s, the length of s is greater than the length s of a driving cycle 1 ;
[0058] S2. Go up step A 1 and down step A 2 The excavation contour lines of the peripheral holes Z are arranged.
[0059] S3. Go up step A 2 vertical line B 0 On both sides of , symmetrically arrange i parallel to the mid-perpendicular line B 0 The hole vertical line B 1 , B 2 , B 3 , ..., B i , i≥2,; on the upper step A 2 The upper parallel to the tunnel floor is arranged with the hole plane C 1 , C 2 , C 3 , …, C j , j≥1; hole flat line C j with the vertical line B 0 The intersection point is the hole base point B 0 C j , the hole vertical line B 1 , B 2 , B 3 , ..., B...
Embodiment 3
[0069] Taking the track roadway in the west wing of a mine as an example, a single blasting method for a large-section tunnel is described in detail.
[0070] like Figure 4 As shown, the roadway is a straight wall semi-circular arch section, the excavation width is 5.90m, the excavation height is 5.45m, the wall height is 2.50m, and the excavation section area is 28.4m 2 . The diameter of the hole E used in the example is 113 mm, and the diameter of the expanded slot P hole is 42 mm. Using the large-section tunnel primary detonation method of the present invention in roadway excavation, the concrete construction steps include:
[0071] Step 1: Divide the driving section A into the upper step A 1 and down step A 2 Two sections, the height of the upper step is 2.90m.
[0072] Design excavation cycle length h=2.50m, go up to step A 1 Advance down step A 2 Distance s=4.00m.
[0073] Step 2: Go up Step A 1 The peripheral holes Z are arranged on the excavation outline, and...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com