Project investment calculation method based on typical power supply mode
A technology of power supply mode and calculation method, applied in the direction of calculation, resources, instruments, etc., can solve the problem of unsustainable large-scale high-level investment, and achieve the effect of avoiding excessive investment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0050] Embodiment, the application example of Yangzhou City Power Grid, Jiangsu Province;
[0051] (1) There are four types of power supply areas in Yangzhou: A, B, C, and D. The current annual load density of the four types of power supply areas is 7.6000MW / km 2 、2.6403MW / km 2 、0.5098MW / km 2 、0.2388MW / km 2 In 2020, the load densities of the four types in the supply area will be 9.0000MW / km respectively 2 、3.1267MW / km 2 、0.6037MW / km 2 、0.2827MW / km 2 ;
[0052] (2) According to the voltage level sequence of substations in Yangzhou supply area, the number of main transformer configurations, capacity, and outgoing medium-voltage lines, etc., the power supply mode of Yangzhou supply area is selected as A, B, and A-3, B-3 and B-2 Mainly, C and D categories are mainly C-1, C-2, D-2, D-5, a total of seven typical power supply modes;
[0053] (3) According to the project investment model of the above-mentioned typical power supply modes, judge the most economical power supply ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com