Concave building template group construction method

A construction method, concave-shaped technology, applied in building structure, formwork/formwork/work frame, construction, etc., can solve the problems of increased waiting time for construction, inability to form floor walls and partition walls at one time, etc. , to achieve cost savings

Inactive Publication Date: 2017-04-05
李宜君
View PDF8 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0007] Through the above known cases, it can be found that it is hoped that the main body mold can be used to improve the efficiency of building multiple floors, but in fact, there are serious deficiencies in all known cases, because when each floor is to be built, the main body mold must first be raised At least a certain height, spraying the wall with a spraying device, then arranging prefabricated panels and distributing concrete on the top surface of the wall, then spraying the top surface of the wall, and then lowering the main mold to the production floor; In other words, although the use of molds combined with concrete injection can indeed increase the speed of construction, the known construction methods cannot form the walls of the floors and partitions at one time. After the floor wall, it is still necessary to wait for a period of time to build the partition wall to make it completely form a floor. In other words, the more floors are built, the time spent waiting for construction will increase relatively. Still room for improvement

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Concave building template group construction method
  • Concave building template group construction method
  • Concave building template group construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0062] ginseng Figure 1-Figure 25 As shown, the embodiment of the present invention is a construction method of a concave-shaped building formwork group, which uses a concave-shaped floor forming device 10 and a plurality of column devices 20 to construct a building with a concave shape on a foundation T in a fast and convenient manner. A building with multiple floors, wherein the concave-shaped floor forming device 10 includes:

[0063] A carrier 11 with a working space 110, the carrier 11 is roughly rectangular in design, and the top of the carrier 11 straddles a plurality of support plates 111 (can be straddled in a vertical or horizontal manner according to actual needs), each of the There are appropriate gaps 1110 between adjacent support plates 111 and a plurality of suspenders 1111 are fixed downward, and the longitudinal width W of the central position of each support plate 111 is the maximum distance and gradually slopes to both sides, so that the central position of...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a concave building template group construction method. The method comprises the steps that a multi-straight-wall steel reinforcement cage construction work of the first floor is carried out; b a concave floor forming device is provided and arranged on a foundation; c a number of outer wall molds are provided to cover four sides of each room mold; d grouting is carried out on a number of longitudinal passages through all room molds; e multi-straight-wall steel reinforcement cage construction work of an upper floor is carried out; f mold contraction is carried out; g mold lifting is carried out; h a horizontal wall steel reinforcement cage is made; i a number of outer wall molds are provided; j grouting is carried out; and k the steps from e to j are repeated until all floors are completed.

Description

technical field [0001] The invention relates to building construction methods, in particular to a construction method for concave-shaped building formwork groups. Background technique [0002] At present, construction in the construction industry generally uses manual construction of various scaffolds, manual assembly and disassembly of building templates, manual on-site welding of steel bars in walls and columns, and manual handling of templates. Often the quality cannot be guaranteed, labor intensity is high, the construction period is slow, and the cost is high. , And there are many potential safety hazards. [0003] However, in today's society where labor costs are gradually increasing, in order to solve the above problems, it is necessary to provide a method for rapid mechanized construction of high-rise buildings that can improve construction safety and reliability, greatly increase construction speed, ensure construction quality, and reduce construction costs. techno...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E04G21/00E04G11/02E04G11/20
CPCE04G21/00
Inventor 李渊河
Owner 李宜君