Construction method of foundation pit supporting and earth excavation of building basement

A technology of earth excavation and foundation pit support, which is applied in construction, infrastructure engineering, excavation, etc., can solve problems such as foundation pit instability and affect the structural strength of buildings, and achieve the effect of strong resistance

Inactive Publication Date: 2018-02-16
广州市番禺区第五建筑工程公司
View PDF2 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] For example, the basement level of a certain engineering project is 6628 square meters, and there are 11 floors above the ground, with an area of ​​46720 square meters. PHC-AB500 hammer pipe piles are used for extrusion; the foundation pit soil layer from top to bottom includes: manual filling Soil (thickness 2.8-3.4m), muddy soil (thickness 2.2-5.5m); the groundwater of the site is pore water, which is mainly supplied by atmospheric precipitation and lateral seepage of the aquifer. If the building is built above the groundwater, the foundation pit may be unstable; if the building is built under the groundwater, the structural strength of the building will still be affected under the long-term erosion of the groundwater

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of foundation pit supporting and earth excavation of building basement
  • Construction method of foundation pit supporting and earth excavation of building basement
  • Construction method of foundation pit supporting and earth excavation of building basement

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0055] A construction method for foundation pit support and earth excavation of building basement, such as figure 1 As shown, it mainly includes the following 6 main steps:

[0056] S1: Leveling the site, laying the sideline, construction axis, and mixing pile position;

[0057] S2: Mixing pile construction;

[0058] S3: Prestressed pipe pile construction;

[0059] S4: Drainage system on top of foundation pit;

[0060] S5: Excavate earthwork;

[0061] S6: Set up the drainage system at the bottom of the foundation pit.

[0062] Before the actual construction, it is necessary to investigate and record the original conditions of the roads and pipelines around the foundation pit before excavation; and to do a good job of drainage, water stop and precipitation measures for the foundation pit. Pay close attention to the foundation pit excavation process. Pit stop water problem, avoid the emergence of water leakage, water seepage and piping.

[0063] Determine the side line of the foundation pit...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
Long diameteraaaaaaaaaa
Lap lengthaaaaaaaaaa
Pile lengthaaaaaaaaaa
Login to View More

Abstract

The invention relates to a construction method of foundation pit supporting and earth excavation of a building basement. The construction method comprises the following steps that S1, a site is leveled, side setting-out of an edge line is conducted, the axis is constructed, and the pile position of a stirring pile is determined; S2, the stirring pile is constructed; S3, a prestressed pipe pile isconstructed; S4, a foundation pit top drainage system is constructed; S5, earth is excavated; and S6, a foundation pit bottom drainage system is arranged. A building is arranged under underground water, and therefore water stopping or drainage devices such as a water stopping curtain and a water collection well are arranged on the peripheral side of a foundation pit. As for blocking of surface water, the main steps are that a water blocking concrete foundation is arranged on the top of a side slope; the top of the slope is slightly high, so that the surface water is drained into a drainage ditch outside the foundation pit; and meanwhile the ground on the top of the slope is subjected to hardening treatment, so that the surface water and rainwater are prevented from permeating into a protecting wall of the side slope. The drainage ditch and the water collection well are arranged in the foundation pit along the periphery of the foundation pit according to the design requirement, water inthe foundation pit is drained timely, and the situation that the surface water or the underground water affects the structural strength of the foundation pit is avoided.

Description

Technical field [0001] The invention relates to a building construction method, in particular to a construction method for foundation pit support and earth excavation of a building basement. Background technique [0002] With the popularity of large-scale engineering projects with basements, special construction schemes for foundation pit support and earth excavation play an important role in large-scale engineering projects with basements. [0003] For example, the underground floor of an engineering project is 6,628 square meters, and there are 11 floors on the ground with an area of ​​46,720 square meters. The extrusion adopts PHC-AB500 hammered pipe piles; the engineering foundation pit soil layer from top to bottom includes: manual filling Soil (thickness 2.8-3.4m), silty soil (thickness 2.2-5.5m); the groundwater of the site is pore water, which is mainly recharged by atmospheric precipitation and lateral seepage of aquifers. The groundwater level is high and it is close to t...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D17/02E02D17/04
CPCE02D17/02E02D17/04E02D2600/40
Inventor 欧阳子雄陈文伟何兆强
Owner 广州市番禺区第五建筑工程公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products