Construction method of interlocking comprehensive pipe gallery

A construction method and a technology of comprehensive pipe gallery, applied in artificial islands, water conservancy projects, infrastructure engineering, etc., can solve the problems of prefabricated wall panels such as difficult prefabrication, complicated process, and low efficiency, and achieve convenient connection and adjustment process and simplified assembly The process of construction, making simple effects

Active Publication Date: 2020-04-07
CHINA METALLURGICAL CONSTR ENG GRP
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0005] In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is to provide a construction method for an interlocking integrated pipe gallery, which avoids the difficulty of prefabrication of prefabricated wall panels, and the process of combining prefabricated wall panels into a superimposed wall is complex and efficient. The problem is that only one structural type of prefabricated wall panels is needed to achieve the side wall of the entire pipe gallery, which simplifies the entire assembly and construction process and improves the construction efficiency.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of interlocking comprehensive pipe gallery
  • Construction method of interlocking comprehensive pipe gallery
  • Construction method of interlocking comprehensive pipe gallery

Examples

Experimental program
Comparison scheme
Effect test

specific Embodiment 1

[0057] see figure 1 , figure 2 , the construction method of the interlocking integrated pipe gallery of the specific embodiment 1 includes several interlocking single-piece prefabricated wall panels 10 used in the construction process, and the interlocking single-piece prefabricated wall panels 10 include vertical The wallboard 1, along the length direction of the wallboard 1, on one side of the wallboard 1, two buckle ribs 2 extending in the vertical direction and having an "L" shape in horizontal section, the buckle ribs The board 2 includes a vertical side 21 perpendicular to the wallboard 1 and fixedly connected to the wallboard 1 and a parallel side 22 connected to the free end of the vertical side 21 and parallel to the wallboard 1, and the two vertical sides 21 are flush up and down, The distances from the two parallel sides 22 to the wallboard 1 are the same and both face the same direction; the sum of the vertical distances from the two ends of the wallboard 1 to th...

specific Embodiment 2

[0077] The difference between specific embodiment two and specific embodiment one is: see Figure 8 , Figure 9 The interlocking single-piece prefabricated wall panels 10 used in the construction method of the interlocking integrated pipe gallery in the specific embodiment 2 are arranged at intervals on one side of the wall panel 1 along the length direction of the wall panel 1. One buckle rib panel 2 extending in the vertical direction, the vertical sides 21 of the four buckle rib panels 2 are arranged symmetrically with the median planes 211 of the two vertical sides 21 closest to the two ends of the wallboard 1 to ensure two identical structures All the parallel sides 22 of the interlocking type monolithic prefabricated wall panels 10 can be interlocked in pairs, and the distances from the parallel sides 22 of the four buckle rib panels 2 to the wall panels 1 are consistent and all face the same direction; The vertical distance from the end face of the upper parallel side ...

specific Embodiment 3

[0081] The difference between specific embodiment three and specific embodiment one is: see Figure 12 , Figure 13 , the interlocking single-piece prefabricated wall panel 10 used in the construction method of the interlocking integrated pipe gallery in the third embodiment is provided with five intervals on one side of the wall panel 1 along the length direction of the wall panel 1. One buckle rib plate 2 extending in the vertical direction, the vertical sides 21 of the five buckle rib plate 2 are set in a symmetrical form with the median planes 211 of the two vertical sides 21 closest to the two ends of the wallboard 1 to ensure two identical structures All the parallel sides 22 of the interlocking type monolithic prefabricated wall panels 10 can be interlocked in pairs. Since the number of the interlocking ribs 2 is an odd number, the middlemost one of the buckling ribs 2 is located on the median plane. 211, the distance between the parallel side 22 of the five-way clasp ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method of an interlocking type comprehensive pipe gallery. The interlocking type comprehensive pipe gallery comprises interlocking type single prefabricated wall boards. Each interlocking type single prefabricated wall board comprises a vertical wall board body, wherein in the length direction of the wall board body, at least two interlocking rib plates arearranged on one side face of the wall board in a spaced manner and extend in the vertical direction, wherein the horizontal section of each interlocking rib plate is in an L shape. The construction method comprises the steps that (1) two interlocking type single prefabricated wall boards are oppositely arranged in parallel, the side faces with the interlocking rib plates are outward, a supportingdevice is erected between the two interlocking type single prefabricated wall boards, and an assembling component is formed; (2) a plurality of assembling components are erected in the length direction of the pipe gallery, the two interlocking type single prefabricated wall boards of each assembling component are located on the two vertical faces correspondingly, and all the parallel edges on thesame side face the same direction; (3) the outer side of each the interlocking type single prefabricated wall board is correspondingly connected with one interlocking type single prefabricated wall board. By the adoption of the construction method of the interlocking type comprehensive pipe gallery, just one structural manner of interlocking type single prefabricated wall boards are needed, and the whole pipe gallery construction process is simplified.

Description

technical field [0001] The invention belongs to the technical field of underground structures in fixed buildings, and in particular relates to a construction method of an interlocking comprehensive pipe gallery. Background technique [0002] At present, with the continuous development of the economy and the acceleration of urban construction, infrastructure construction is indispensable. As a construction facility built underground in the city to accommodate urban engineering pipelines, the pipe gallery is an important part of urban infrastructure construction. Comprehensive management Corridor, also known as "common ditch" and "common pipeline", is to build a tunnel space underground in the city, integrating various engineering pipelines such as electricity, communication, gas, heating, water supply and drainage, and implementing unified planning. [0003] The side wall of the pipe gallery is usually a prefabricated hollow laminated wall to facilitate the pouring of concret...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045
CPCE02D29/10
Inventor 魏奇科王振强王维说宋春芳廖小辉陈豪方蒙周冀林成治张从洋
Owner CHINA METALLURGICAL CONSTR ENG GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products