Performance tester for gel valve in the course of underbalance well drilling and well completion and application thereof
An underbalanced drilling and tester technology, applied in the field of oil and gas field drilling, can solve problems such as failure to perform accurate evaluation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0029] This example evaluates the jelly strength of the jelly valve at 90°C.
[0030] (1) Close the first pressure reducing valve 2, the flow meter 3, the lower end pressure valve 6, install the bottom cover 15, put the temperature control probe 12 into the temperature control hose body 8, and preheat the instrument to 90°C;
[0031] (2) Put the gasket into the temperature-controlled rubber tube body 8, spread it flat on the pressure hole at the lower end, then pour the prepared solution to be gelled, install the top cover 13, and heat for 5 hours;
[0032] (3) Before the test, turn off the temperature controller 5, pull out the temperature controller probe 12, and remove the top cover 13;
[0033] (4) Open the lower end pressure valve 6 (note that the flow meter is closed at this time, because the large pipe pressure is high, the liquid is easy to flow back, so the lower end pressure valve cannot be opened too large), and then open the first pressure reducing valve 2, when th...
Embodiment 2
[0037] This example evaluates the jelly strength of the jelly valve at 120°C.
[0038] (1) Close the first pressure reducing valve 2, the flow meter 3, the lower end pressure valve 6, install the bottom cover 15, put the temperature control probe 12 into the temperature control hose body 8, and preheat the instrument to 120°C;
[0039] (2) Put the gasket into the temperature-controlled plastic tube body 8, and spread it flat on the pressure hole at the lower end, pour the prepared gel solution into the temperature-controlled plastic tube body 8, install the top cover 13, and Heating at 120°C for 5h;
[0040] (3) Before the test, close the temperature controller 5, pull out the temperature control probe 12; remove the top cover 13;
[0041] (4) Open the lower end pressure valve 6 (note that the flow meter is closed at this time, because the large pipe pressure is high, the liquid is easy to flow back, so the lower end pressure valve cannot be opened too large), and then open t...
Embodiment 3
[0045] This example analyzes the jelly airtightness strength of the jelly valve.
[0046] (1) Close the first pressure reducing valve 2, the flow meter 3, the lower end pressure valve 6, install the bottom cover 15, put the temperature control probe 12 into the temperature control hose body 8, and preheat the instrument to 80°C;
[0047](2) Pour in the prepared solution to be gelled, install the top cover 13, and heat for 5 hours;
[0048] (3) Before the test, close the temperature controller 5, pull out the temperature control probe 12; remove the top cover 13;
[0049] (4) Open the lower end pressure valve 6 (note that the flow meter is closed at this time, because the large pipe pressure is high, the liquid is easy to flow back, so the lower end pressure valve cannot be opened too large), then open the first pressure reducing valve 2, when the control When the temperature-controlled hose body 8 has an outer diameter of 2in and a height of 30cm, the pressure does not exceed...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More - R&D
- Intellectual Property
- Life Sciences
- Materials
- Tech Scout
- Unparalleled Data Quality
- Higher Quality Content
- 60% Fewer Hallucinations
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2025 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com