Storage yard effective volume optimum control method based on dredged sediment original state control
A technology with initial state and effective volume, applied in the fields of waterways, water conservancy projects, and ports, it can solve the problems of unconsidered, increase the natural sedimentation rate of muddy water, and accelerate the generation of surface water, so as to reduce the use area, shorten the completion time, and reduce the water content. effect of water
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2018-03-06
- Estimated Expiration
- Not applicable · inactive patent
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The invention belongs to the technical field of ports, waterways and water conservancy projects, and is an optimal control for dredging mud produced in the construction of water conservancy, port wharves and waterway projects to promote the rapid separation of mud and water by controlling the initial state to achieve the effective volume of the storage yard. Large-area comprehensive disposal project of low-concentration dredged mud. Background technique
[0002] In order to improve the water quality of rivers and lakes, ensure the normal flood discharge capacity of rivers and the smooth flow of inland waterways, my country has to carry out large-scale dredging and dredging projects every year. It is inevitable to produce a large amount of dredging mud. According to incomplete statistics, various types of dredging mud discarded in my country reach hundreds of millions of cubic meters every year, and the engineering volume of dredging mud treatment is hu...
Examples
Embodiment 1
[0023] In the dredged mud stockpile, the following steps are used to achieve rapid deposition and reduce the water content of the dredged mud to achieve the optimal control of the effective volume of the stockpile.
[0024] The specific steps and contents of the construction are as follows:
[0025] (1) Arrange the space drainage system in the weir before mud discharge, such as figure 1 Shown:
[0026] First, the water filter drain pipe 2 is laid step by step in the bottom horizontal direction in the cofferdam 1 and the drain pipe 3-1 is laid in the vertical direction at the bottom thereof, and the water filter drain pipe 2 and the drain pipe 3-1 are connected to each other. connected, and a drainage pipe 3-2 is arranged at the bottom of the cofferdam. The drainage pipe 3-2 communicates with the drainage pipe 3-1 and extends through the bottom of the cofferdam to the outside of the cofferdam, and the outlet of the drainage pipe 3-2 is lower than Elevation of the bottom in th...