Disaster recovery regulation and control management method and system

A management method and technology for a backup system, applied in the field of disaster recovery regulation and management methods and systems, can solve the problems of inability to guarantee RTO, lack of disaster recovery regulation management means, and high requirements for maintenance capabilities, so as to reduce uncertain risks and improve management efficiency. , The effect of reducing the risk of operation and maintenance

Pending Publication Date: 2020-05-12
GUANGDONG ELECTRIC POWER COMM CO LTD +1
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In order to verify the effectiveness of the disaster backup system and ensure that the disaster backup system can successfully take over the operation of the production system, it is necessary to carry out disaster switchover drills. However, there is currently a lack of effective and reliable disaster recovery control and management methods, and the switchover can only be achieved manually. There are many problems in the model: administrators switch each application system independently and independently; the degree of automation and intelligence is low, the requirements for maintenance capabilities are high, and the maintenance intensity is high; there is no unified management tool and view, and switching management is passive; RTO cannot be guaranteed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Disaster recovery regulation and control management method and system
  • Disaster recovery regulation and control management method and system
  • Disaster recovery regulation and control management method and system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0041] A disaster recovery control and management method in this embodiment is based on the application-level disaster recovery system construction project of the Guangzhou Power Grid Information Center enterprise-level system, and includes the following steps:

[0042] S00: For the existing customer systems, establish corresponding pre-plan scripts one by one; the pre-plan scripts include the switching process and various scripts corresponding to the switching process;

[0043] S10: Perform drill switching on the scenario scripts, form a drill report, retain the scenario scripts that can complete the disaster recovery switching task according to the drill report, and further improve and modify the scenario scripts that cannot complete the disaster recovery switching task;

[0044] S20: Monitor the existing client system, if there is a client system that has a disaster, call the pre-plan script of the client system and add it to the disaster switching list;

[0045] S30: Execu...

Embodiment 2

[0055] This embodiment discloses a disaster recovery control management system, including:

[0056] Pre-plan generation module, used to establish its corresponding pre-plan script according to the client system;

[0057] The drill module is used to drill the scenario script generated by the scenario generation module and generate a drill report;

[0058] The scenario management module is used to keep available scenario scripts and re-edit unavailable scenario scripts according to the drill report;

[0059]The disaster switch module is used to call and execute the corresponding available plan scripts from the plan management module according to the current disaster client system to perform disaster backup switch;

[0060] The display module is used to provide multi-level views for different user groups, and the element information of the views includes the proportion of the switching progress, the completion of the switching stage, the execution of the switching process under ...

Embodiment 3

[0063] Such as figure 1 As shown, a disaster recovery regulation and management system of this embodiment includes a presentation layer, a business layer, a basic service layer and a data layer. The presentation layer of this embodiment is used to provide multi-level view services according to different user groups, and the business layer uses It is responsible for the processing of business in the system field, the generation, processing and conversion of logical data; the basic service layer is used to provide service support for the business layer, and the data layer is used to operate related databases.

[0064] Specifically, the presentation layer of this embodiment includes:

[0065] Leadership view for leadership decision-making users, whose view element information includes the name of the switching drill plan, personnel sign-in, application system category statistics, data center switching statistics, switching process, operation overview, RTO / RPO indicator overview, ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a disaster recovery regulation and control management method and system. According to an application-level disaster recovery system construction project based on an enterprise-level system of a Guangzhou power grid information center, comprehensive centralized management and scheduling integrating functions of disaster recovery system switching control scheduling, disaster recovery switching process display, disaster recovery plan (DRP) management and the like are integrated; and when a disaster occurs in the production system, the production system is switched to the disaster recovery system through the disaster recovery regulation and control management system according to a predefined process, and after the production system returns to normal, the production system is switched back to the production system from the disaster recovery system.

Description

technical field [0001] The invention belongs to the field of information technology, and more specifically relates to a disaster recovery regulation and management method and a system thereof, which are mainly responsible for managing enterprises and application systems of a production center and a disaster recovery center. Background technique [0002] For enterprises, disaster recovery can only guarantee the relative integrity of the data system after a disaster occurs, that is, the question of "how much data will be lost once a disaster occurs". But business continuity management solves the business recovery ability of the enterprise after the disaster occurs, that is, "once the disaster occurs, how much business can the enterprise recover within a short period of time". At present, there is no relevant information system that can realize effective management and control of disaster recovery. [0003] In order to ensure the continuous and stable operation of the company'...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06G06Q50/06
CPCG06Q10/06G06Q50/06
Inventor 肖建毅曾朝霖邱宇马瑞雯唐亮亮王均曹存洋汪林鹿泉卞辉辉陶学林孙雨辰
Owner GUANGDONG ELECTRIC POWER COMM CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products