A construction method for planting carpet plants on roofs for water conduction and waterproofing
A construction method and carpet-like technology, which can be applied to roofs, roof coverings, building structures, etc., can solve problems such as the inability to plant S. japonica carpet plants, aging of roofing materials, and water leakage.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0021] The construction method of planting S. japonica on the cement roof for water conduction and waterproofing includes the following steps:
[0022] 1. Clean the roof to keep the roof flat;
[0023] 2. The drainage slope of the roof should reach 1%-3%. If the slope is not enough, the cement surface should be re-paved to find the slope;
[0024] 3. To clear the sewer, it is necessary to ensure that the drainage pipes are unblocked. Because of the cold winter in the buildings in the northern region, in order to prevent the downpipes from freezing and blocking, it is advisable to use internal drainage, that is, the downpipes are located on the inside of the outer wall; buildings in the southern region generally use external drainage. , the most commonly used drainage methods are the drainage outside the parapet wall and the drainage outside the gutter;
[0025] 4. For the water pipes of cement roofs, the materials generally selected in the northern region are cast iron draina...
Embodiment 2
[0031] The construction method of planting S. japonica on the iron roof for water conduction and waterproofing includes the following steps:
[0032] 1. Clean the roof to keep the roof clean;
[0033] 2. For iron sheet factory buildings over one year old, it is necessary to check whether there is water leakage at the joints of the iron sheet roof and the iron nails. If there is, it is necessary to repair the leakage;
[0034] 3. Iron sheet factory buildings with a building age of more than two years must be treated with roof iron sheets, and all rust spots should be coated with antirust agents;
[0035] 4. After the leakage and anti-rust work, lay self-adhesive modified asphalt waterproof coiled board on the roof, the thickness of the coiled board is 2.5-3mm (national standard), and keep the aluminum-coated film on the upper surface of the coiled board, see figure 1 ;
[0036] 5. Lay recycled plastic gutters, and select the corresponding gutters according to the thickness of...
PUM