Reinforcing construction method for trough plate platform of operation subway station
A construction method and technology for subway stations, applied in building maintenance, construction, building construction, etc., can solve the problems of poor reinforcement effect and high safety risks, and achieve the effect of improving workers' work efficiency, ensuring operational safety, and ensuring quality.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Example Embodiment
[0028] Attached below figure 1 , Attached figure 2 A detailed description of the present invention:
[0029] reference figure 1 , figure 2 , It includes 1 for chemical anchor bolt; 2 for angle steel bracket; 3 for bottom steel form; 4 for side steel form; 5 for pouring trough; 6 for high funnel; s1: please click to block the track line; s2: construction preparation; s3 : Take the hole; s4: steel bar installation; s5: steel formwork installation; s6: cement-based grout mixing; s7: cement-based grout pouring and high-level funnel pressurization; s8: platform restoration; s9: point elimination, remove line blockade ;
[0030] The specific implementation steps are as follows:
[0031] A construction method for reinforcing trough slab platform of an operating subway station. The construction includes the following steps:
[0032] s1: Please click to block the track line: please click to the operation dispatching room to block the track line in the designated area to ensure the safety...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap