A split origination and vertical shaft technology, which is applied in the direction of earth drilling, mining equipment, tunnels, etc., can solve the problems that the auxiliary equipment cannot be arranged on both sides of the trolley, the impact of cross construction is large, and the efficiency of shield tunneling is low. Achieve the effect of reducing shield supporting equipment and personnel input, saving construction period and cost, and saving split starting pipelines
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0048] Such as figure 1 As shown, it is a flowchart of a method for two-way splitting of a small shield in a narrow shaft according to the present invention. The specific implementation process includes the following steps:
[0049] S1:
[0050] ①. Design and customize a small shield machine according to the tunnel design requirements, shield excavation stratum characteristics, safety risks and other factors. Due to the small section of the tunnel, the supporting equipment behind the shield machine is arranged on the side of the trolley;
[0051] ②. According to the overall layout of the site, install the split starting pipeline required for the connection between the upper trolley and the underground trolley. Layout of shield supporting functions such as mixing station and cooling tower;
[0052]③.Use the gantry crane to hoist the starting bracket and the reaction frame into the well for installation and positioning. After the 1# shield machine enters the site, use the gant...