Treatment and construction process for tunnel to pass through super-huge karst cave with water cavity
A kind of construction technology and super-large technology, applied in tunnels, tunnel linings, drainage and other directions, can solve the problems of large construction disturbance of surrounding rock, complicated construction technology, long construction time, etc., to achieve less construction difficulty, less impact, and lower construction costs. and duration effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0030] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0031] The present invention provides a treatment and construction process for a tunnel passing through a super-large water cavity karst cave, which includes the following steps:
[0032] Step 1: Protect the top of the cave to prevent rockfall on the top of the cave from posing a safety threat to the construction workers at the bottom of the cave. (1) Construction of temporary passive protective net, adopting a protective form similar to active protective net; (2) Ground anchor links are used on both longitudinal sides of the karst cave. The embedded length of the rod is 4.5 meters, and the top of the anchor rod is anchored with C30 reinforced concrete; (3) An elbow is installed at the end of the Φ22 anchor rod to connect firmly with the steel wire rope, and a protective net is set on the steel wire rope (the protective net includes steel wire rope net,...