Construction method of expansive soil stratum shield underneath pass railway track
A technology of railway tracks and construction methods, which is applied in underground chambers, earthwork drilling, tunnels, etc., can solve the problems of safety impact of tunnel buildings, instability of excavation surface, poor effect, etc., and achieve reduction of mutual influence and reinforcement The effect of surface soil layer and convenient method
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2021-03-16
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of shield tunneling structure construction, in particular to a construction method for tunneling a railway track by a shield tunneling in an expansive soil layer. Background technique
[0002] With the rapid development of underground transportation in our country, domestic subway projects are facing some technical problems. At present, the shield tunneling method has become the preferred tunnel construction method in the field of underground engineering. There are many project cases where the shield machine passes under the railway line. It is important. For underground engineering in expansive soil layers, the development of the project has certain challenges. When the soil loses water excessively, its volume begins to shrink and cracks occur; conversely, when the soil moisture of expansive soil increases , the soil will expand and generate a pressure, which will easily cause water gushing and cause the e...
Examples
Embodiment 1
[0028] Such as figure 1 , figure 2 as shown, figure 1 It is a flow chart of the construction method for the shield tunneling under the expansive soil layer to pass through the railway track, figure 2 It is a schematic diagram of the shield tunneling under the railway track; the construction method of the shield tunneling under the expansive soil layer of the present invention comprises the steps of:
[0029] S1, using finite element analysis software to simulate engineering;
[0030] S2, improving the expansive soil mass;
[0031] S3, pouring slab isolation foundation under the track;