Operation method for replacing 10kV drop-out fuse in on-load manner

A drop-out fuse and load-carrying technology, applied in the direction of overhead lines/cable equipment, etc., can solve problems such as many safety factors, high technical level requirements for operators, and short distance between phases, so as to reduce failure rate, improve power supply quality, The effect of using fewer tools
CN102931609AActive Publication Date: 2013-02-13ANSHAN POWER SUPPLY COMPANY OF STATE GRID LIAONING ELECTRIC POWER COMPANY +1

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
ANSHAN POWER SUPPLY COMPANY OF STATE GRID LIAONING ELECTRIC POWER COMPANY
Publication Date
2013-02-13
Patent Text Reader

Abstract

The invention relates to the field of a drop-out fuse in a distribution line of a power grid, and particularly relates to an operation method for replacing a 10kV drop-out fuse in an on-load manner. The operation method is characterized in that an insulation drainage wire bypass drop-out fuse is directly connected with the two ends of the drop-out fuse to be replaced for splitting current, and thus the 10kV drop-out fuse is replaced in the on-load manner and under the condition of continuously charging a load. Compared with the prior art, the operation method has the beneficial effects that the load on the lower end of equipment can be charged continuously in the operation period, and when the on-load operation is implemented by an electrified operation method, the delivery time and the redelivery time of the equipment can be avoided, the operation flow is shortened, and the electricity utilization of a user can not be affected in the operation period; the failure rate of 10kV primary equipment can be reduced greatly, and the power supply quality can be improved effectively; and the drop-out fuse is replaced in the on-load manner and with an insulation drainage wire, the operation is conducted by a double-man double-insulation bucket truck, the operation time is short, few tools are used, resources can be saved effectively, and the power supply reliability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the field of drop-out fuses for power grid distribution lines, in particular to an operating method for replacing 10kV drop-out fuses with load. Background technique

[0002] In the past, there are two main methods for replacing drop-out fuses: one is to stop the load at the lower end of the drop-out fuse, and then use the method of live disconnection and connection of leads to cut off the power supply at the upper end of the drop-out fuse before replacing it; One is to directly cut off the power supply at the upper end of the drop-out fuse for power failure replacement. Although both of the above two methods can replace drop-out fuses, part of the electrical load still needs to be shut down; from the failure of drop-out fuses to the restoration of power supply, certain social impacts and economic losses will still be caused during this period.

[0003] At present, drop-out fuses have not been replaced by insulated drain wires...