Cutting, splitting and breaking transformation construction method for existing overall ballast bed of subway

A technology of integral ballast bed and construction method, which is applied to roads, tracks, laying tracks, etc., can solve the problems of large amount of construction waste, poor economy, and low work efficiency, and achieve the effects of broad promotion prospects, low environmental pollution, and low construction costs

Inactive Publication Date: 2016-02-24
CHINA TIESIJU CIVIL ENG GROUP
View PDF5 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] At present, there is no precedent for existing ballast bed reconstruction under the state of operating lines at home and abroad. If the general chiseling method is used, the investment in equipment and manpower is large, the economy is poor, and the wo

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Cutting, splitting and breaking transformation construction method for existing overall ballast bed of subway

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0009] Referring to the accompanying drawings, it is a construction method of cutting, splitting, breaking, and rebuilding the existing integral track bed of the subway. First, use a wall saw to vertically cut the track bed on the concrete track bed slab 1 along the line lengthwise at an interval not greater than 3.6 cm. The cutting depth is from the concrete surface to the cutting of the steel bar. , but the segment must not be damaged, and then use a core drilling machine to drill holes along the cutting seam. The number of holes is 2 to 6. The splitting rod 2 is inserted into the borehole to adjust the splitting direction, pressurized and expanded until the slab is separated from the pipe wall, and finally the existing slab that has been demolished is lifted by the cantilever crane in the subway tunnel and a new floating slab is constructed to complete the existing whole Track bed renovation.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a cutting, splitting and breaking transformation construction method for an existing overall ballast bed of a subway. The method includes the steps that the ballast bed is perpendicularly cut on a concrete ballast bed plate in the longitudinal direction of a line within the distance of not larger than 3.6 cm through a wall saw, and cutting is conducted to the depth that the part between a concrete face to steel bars is cut off but a pipe piece is not damaged; then, a coring drilling machine is used for drilling along a cutting line, the number of drill holes is 2-6, the diameter of the drill holes is determined according to requirements, the depth of the holes is determined according to the requirement of a splitting bar, the hydraulic splitting bar is inserted into the drill holes to adjust the splitting direction, and pressurizing expanding is conducted until the plate disengages from a pipe wall; and finally, a cantilever crane in a subway tunnel is used for craning the existing broken plate and conducting construction to newly lay a floating plate, and accordingly the transformation of the existing ballast bed is completed. The method is low in construction cost, easy to operate, high in construction speed and low in noise, construction is not stopped on an operation line, safety and reliability are achieved, and the requirements for urban civilized construction, operation line transportation, operation line safety and construction efficiency are met. The popularization prospects are wide.

Description

technical field [0001] The invention relates to the field of subway track bed construction, and in particular belongs to a construction method for cutting, splitting, breaking, and rebuilding existing integral track beds of subways. Background technique [0002] In the bustling area of ​​Shanghai City, near residential areas and commercial areas, the vibration and noise of subway rails are relatively high, which does not meet the environmental protection requirements. It is necessary to remove the entire ballast bed in the existing tunnel and transform it into a vibration-absorbing floating slab. For the track bed, this construction is the first time at home and abroad, and there are no design and construction precedents to learn from. Relying on the simulated non-stop construction of the Expo Park section of Shanghai Metro Line 13, we have made targeted choices in the selection of demolition machinery and equipment and method design, ensuring the smooth and safe completion ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E01B29/00
CPCE01B29/00E01B2204/09
Inventor 殷业锁贾炳义周登辉沈韫龚元朱炎新年胜利雷鸣王薇施海凤
Owner CHINA TIESIJU CIVIL ENG GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products