Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

464 results about "Track bed" patented technology

The track bed or trackbed is the groundwork onto which a railway track is laid. Trackbeds of disused railways are sometimes used for recreational paths or new light rail links. According to Network Rail, the trackbed is the layers of ballast and sub-ballast above a prepared subgrade/formation (see diagram). It is designed primarily to reduce the stress on the subgrade.

Construction method for two-block unballasted track bed board

The invention relates to a construction method for a double-block-type ballastless track bed slab, which comprises the following steps: 1, clearing a base surface and performing construction lofting; 2, placing a bottom layer of reinforcing steel bars, and laying sleepers; 3, mounting a tool track and adjusting the sleepers; 4, assembling track panels; 5, coarsely adjusting the track panels; 6, binding the reinforcing steel bars and performing earthing welding; 7, mounting templates and finely adjusting the track; 8, casting concrete into the track bed slab; 9, loosening adjusting devices and fasteners, and curing the concrete; and 10, relocking the tool track and completing the measurement. The construction method has the advantages that: the tool track is adopted as a detection standard, so the precise positioning of the track is realized; a frock system is simple, is easy to process and manufacture, has wide commonality, and is not only suitable for construction of the track bed slab in a subgrade section but also suitable for construction of the track bed slab in a bridge section; the construction process is simple and quick, and various working procedures are easily carried out by flow construction; and the construction cost is low, so the construction investment is effectively saved.
Owner:THE 8TH GRP OF CHINA RAILWAY 1ST ENG CO LTD

Method for determining capability of resisting slab staggering and expanding deformation of joints between shield tunnel lining rings

The invention provides a method for determining the capability of resisting slab staggering and expanding deformation of joints between shield tunnel lining rings. The method comprises the steps that firstly, the design information of a shield tunnel is obtained; secondly, the longitudinal equivalent bending rigidity and the longitudinal equivalent shearing rigidity of a Timoshenko beam tunnel model are determined by combining the lining design information of the tunnel and the design information of the shield tunnel; thirdly, measuring points are embedded in a track bed of the tunnel, and the settlement volumes of all the longitudinal lining rings of the tunnel are determined; fourthly, fitting is conducted on settlement monitoring values of the tunnel through the Gaussian curve, a fitting equation of a settlement curve is obtained, and the range of the influence of a settlement funnel is judged; fifthly, rotating angles of the lining rings of the tunnel are determined by using the fitting equation of the settlement curve and combining the longitudinal equivalent bending rigidity and the longitudinal equivalent shearing rigidity of the tunnel; sixthly, the expansion amount of the joints of the rings and / or the slab staggering amount between the rings are / is determined. The method is simple, practical, convenient to popularize and suitable for determining the capability of resisting slab staggering and expanding deformation of the joints between the shield tunnel lining rings.
Owner:SHANGHAI JIAO TONG UNIV

Slab end isolation mounting device for floating track bed

The invention belongs to the field of vibration control and relates to a slab end isolation mounting device for supporting a floating slab in a floating track bed. The slab end isolation mounting device comprises a top slab, a bottom slab, an elastic element and a damping element, wherein the elastic element and the damping element are arranged between the top slab and the bottom slab. The slab end isolation mounting device is characterized in that the top slab is provided with a slab end horizontal limiting device; the slab end horizontal limiting device comprises a slab end transverse limiting device or/and a slab end lengthwise limiting device. The slab end isolation mounting device and a prefabricated short slab in the length of 1.2-8m form the structure of the floating track bed together, the prefabricated production and lifting construction of the floating slab are possible, and the prefabricated short slab is limited lengthwise and transversely through the slab end horizontal limiting device, so that the stability and safety of the structure of the floating track bed in the travelling process are guaranteed, the construction speed is greatly improved, the construction period is further shortened, the construction difficulty is reduced, and the production cost is saved. The isolation mounting device is high in practicability, safe, reliable and high in cost performance and has a wide market application prospect.
Owner:GERB QINGDAO VIBRATION CONTROL +1

Steel reinforcement cage track skeleton method construction process of steel spring floating plate track

The invention discloses a steel reinforcement cage track skeleton method construction process of steel spring floating plate track, which comprises the following steps of: 1. preparing construction; 2. pouring and constructing a floating plate foundation and simultaneously assembling a floating plate steel reinforcement cage track skeleton; 3. sequentially hoisting the assembled floating plate steel reinforcement cage track skeleton to the constructed floating plate foundation by sections and positioning and trimming; 4. carrying out erection, track geometric dimension adjustment and pouring construction on the hoisted floating plate steel reinforcement cage track skeleton and carrying out floating plate foundation pouring and floating plate steel reinforcement cage track skeleton assembly so as to ensure that three processes of the floating plate foundation pouring construction, the floating plate steel reinforcement cage track skeleton section assembly and concrete track bed plate pouring construction are simultaneously and continuously carried out respectively; and 5. carrying out reinforced concrete track bed plate lifting construction. The invention has reasonable design, simple construction step, time and manpower saving and high construction efficiency and can effectively solve the practical problems of high construction difficulty and high technical requirement, complicated construction procedures and low construction speed of the floating plate track.
Owner:CHINA RAILWAY FIRST GRP CO LTD +1

Unballasted track bed plate construction method

ActiveCN101195983ASolve technical difficulties in constructionImprove construction qualityRailway track constructionArchitectural engineeringBridge deck
The invention relates to a construction method of the bottom seat plate of the ballastless track, which belongs to a construction process method of tracks. The purpose of the invention is to provide a reliable construction method of the bottom seat plate of the ballastless track on bridges to meet the quality and accuracy requirement of the bottom seat plate of the ballastless track. The construction method comprises the following steps: step one, firstly, the bridge floor is checked and accepted and assessed before planking; secondly, the stakingout connecting line of the bottom seat plate is measured; thirdly, the connection of the fixed bolt is arranged; fourthly, a sliding layer with two cloth and one film is laid on the bridge floor of the box-beam bridge; step two, a hard plastics foam layer is laid on the two ends of the beam slot; step three, a post casting strip connector is installed; step four, firstly, tooth socket welding studs are installed; secondly, bottom seat plate reinforcing bars are installed; step five, bottom seat plate mould plates are installed; step six, the concrete of the bottom seat plate is cast; step seven, the cast post casting strip and the welding stud tooth socket are fixedly connected, and the connection of the bottom seat plates is completed.
Owner:CHINA RAILWAY NO 2 ENG GRP CO LTD

Vibration isolating support structure of damping spring floating track bed and installation method thereof

The invention discloses a vibration isolating support structure of a damping spring floating track bed and an installation method thereof, which comprises a pre-buried sleeve (9) and a vibration isolator component (10). The pre-buried sleeve (9) is cast in a floating plate type track bed body (14) as a whole, bearing convex tables (3, 4 and 17) are fixedly arranged in the pre-buried sleeve (9), a pre-buried anchor bar (8) which extends into the bed body is arranged outside of the pre-buried sleeve (9), and the vibration isolator component (10) is arranged in the pre-buried sleeve (9) and can support the floating plate type track bed body (14) and isolate the vibration of the floating plate type track bed body (14) through the pre-buried sleeve (9). The vibration isolating support structure can provide emergency safety measures under the extreme condition, so that when the fatigue fracture of a large quantity of support springs occurs suddenly, the local settlement of the floating plate type track bed can be limited within the safety limit range of a few millimeters, thereby preventing the spring breakage accident to endanger the safe running of trains, and greatly improving the security coefficient of the floating plate type track bed.
Owner:BEIJING JIUZHOUYIGUI SHOCK & VIBRATION ISOLATION

Method for measuring load threshold of geotechnical packing accumulated deformation state under cyclic loading

The invention relates to a method for measuring load thresholds of geotechnical packing accumulated deformation states under cyclic loading. According to the method, brick walls and sand bags are adopted to construct a filling model, so as to form a testing system along with loading equipment and a displacement sensor, and a cyclic loading test is performed on the filling model, so as to obtain a changing curve of accumulated deformation with loading times; then the changing curve of segmented single loading average deformation with the loading times is obtained through calculation, and a negative power function as shown in the specification is adopted to fit, so as to obtain a relation curve of a power exponent Pi value with the change of load levels; a function relation between the Pi value and the load levels is obtained by virtue of cubic polynomial regression, and the corresponding load levels when P is equal to 2, 1 and 0 are obtained through back calculation, so as to be used as the load thresholds delta t1, delta t2 and delta t3 for distinguishing different evolution states of the accumulated deformation, wherein an experimental basis is respectively provided for design and maintenance of ballastless and ballast track bed structures of railways by the delta t1 and delta t2. The method has the advantages of convenience in model manufacturing, low cost, simplicity in operation and clear distinguishing criterion, and the obtained load thresholds are accurate and reliable.
Owner:SOUTHWEST JIAOTONG UNIV

Construction apparatus of double-block ballastless track and construction process

The invention discloses construction equipment and a construction process for a double block type unballasted track, belonging to the railway track construction field. The construction equipment comprises combined type track panels which are matched to use, a proper motion type paver, a multifunctional electric control lifting device, a movable type mechanical sleeper distribution assembly platform and a shunting swing bridge; under the conditions of meeting the construction quality and the construction efficiency, the construction equipment has the advantages of small number of device categories, simple equipment operation, high construction efficiency and low cost of the outfit. The construction process comprise the following steps: the transverse template mounting, the sleeper distribution and the track panel assembly, the coarse adjustment of track panels, the track bed reinforcing fabric seizing and the grounding welding, the connection and the accurate adjustment of the track panels, the vertical template mounting, the track bed concrete pouring and the surface finishing and forming, the curing and the track panel disassembly, reentering the circle; the process has the advantages of simple process and fast speed; therefore, the invention can completely meet requirements of high standard, high accuracy and high efficiency in the construction of the unballasted track.
Owner:北京铁五院工程机械有限公司 +2

Ballastless track construction method with sleepers arranged firstly and rail panel assembled later

A ballastless track construction method with sleepers arranged firstly and rail panel assembled later comprises the steps of construction layout, installation of steel bars at a bottom layer of a track bed, dispersion of the sleepers and spacing adjustment, assembly of hoisted rail panel frames, coarse adjustment of rail panels, installation of steel bars at top layers of track bed boards, installation of longitudinal and transverse formworks, comprehensive grounding welding, insulating property test, fine adjustment of the rail panels, concrete pouring construction, concrete curing and removal of bent frame molds. According to the construction method, a method that a gantry crane is used for assembling the rail panels on a mobile assembly platform is changed, a method that the sleepers are arranged firstly and the rail panels are assembled later on a construction operation surface is adopted directly, the usage of the mobile assembly platform is canceled, the problem of land occupation of the mobile assembly platform is solved, and the field change efficiency of other machines, tools and equipment is improved, in addition, a crane instead of the gantry crane is used for matching assembly, so that the gantry crane is mainly used for transferring other light machines, tools and equipment, the safety of transferring hoisting is improved, the continuous construction is guaranteed, the effective utilization rate of the gantry crane is increased, and the construction efficiency is improved.
Owner:CHINA RAILWAY 15TH CONSTR BUREAU GRP +1

Quasi-zero stiffness vibration isolator floating slab track bed and design method thereof

ActiveCN108411713ADoes not affect the bearing capacityStability is not affectedBallastwayIsolation effectEngineering
The invention discloses a quasi-zero stiffness vibration isolator floating slab track bed. The quasi-zero stiffness vibration isolator floating slab track bed is characterized by comprising floating slabs and vibration isolating assemblies disposed in the floating slabs. The vibration isolating assemblies are arranged in the length direction of the floating slabs at intervals. The vibration isolating assemblies comprise outer sleeves cast in the floating slabs and quasi-zero stiffness vibration isolators installed in the outer sleeves. Heightening gaskets for adjusting the height of the floating slabs are arranged between the quasi-zero stiffness vibration isolators and the outer sleeves in a padded mode, the top portions of the outer sleeves are covered with insulating cover plates. According to the quasi-zero stiffness vibration isolator floating slab track bed, the quasi-zero stiffness vibration isolators are arranged in the floating slab track bed, the bearing capacity and stability of a floating slab track are not affected, and the floating slab track bed has the advantages of high bearing capacity, small deformation capability, good low-frequency vibration isolation effect and large vibration isolation frequency range. The low-frequency vibration component of the floating slab track bed is effectively suppressed, and the low-frequency vibration isolation of the floating slab track is realized. The invention further provides a design method of the quasi-zero stiffness vibration isolator floating slab track bed.
Owner:ZHUZHOU TIMES NEW MATERIALS TECH

Monolithic track bed construction process for remodeling ballast track subgrade into ballastless track

A monolithic track bed construction process for remodeling a ballast track subgrade into a ballastless track is characterized by comprising the following steps that a monolithic track bed is cast in place under an auxiliary girder; a track supporting platform mounting groove and a line pipe reserved pipe are reserved during casting; after the monolithic track bed is cast to reach the design strength, the auxiliary girder and an existing track are removed; a track supporting platform is mounted in the track supporting platform mounting groove; and after the track is finely adjusted and fixed, a grouting material is grouted to fix the track supporting platform, wherein the grouting material for fixing the track supporting platform is a high strength non-shrinkage grouting material. The monolithic track bed construction process for remodeling the ballast track subgrade into the ballastless track, provided by the invention is advantaged in that the construction time is greatly reduced, the cost is reduced, resources are saved, the track bed does not need to be integrally pushed and the process is safe and reliable because the monolithic track bed is cast in place under the auxiliary girder. And meanwhile, as the high strength non-shrinkage grouting material is adopted, the grouting operation can be finished within one skylight point and the use strength can be reached to open the line directly within one skylight point.
Owner:THE 3RD ENG CO LTD OF CHINA RAILWAY 18TH BUREAU GRP +1

Easy-to-assemble floating track bed precast slab and application thereof

The invention relates to an easy-to-assemble floating track bed precast slab and an application thereof, which belong to the field of rail transit. According to the invention, the easy-to-assemble floating track bed precast slab can conveniently establish reliable connection with an adjacent floating slab and can smoothly transmit a shear force and improve the force born on the floating slab; and meanwhile, the integrality of a floating track bed structure can be also effectively enhanced, the adaptability of the easy-to-assemble floating track bed precast slab is enhanced and the service life of the easy-to-assemble floating track bed precast slab is prolonged. According to the invention, the easy-to-assemble floating track bed precast slab comprises a precast slab body, wherein the middle part of a connecting end of one side of the precast slab body is fixedly provided with locating guide sleeves; the middle part of a connecting end of the other side of the precast slab body is correspondingly provided with join-assembling holes; the locating guide sleeves and the join-assembling holes are respectively arranged in a longitudinal direction of a track; at least two locating guide sleeves are arranged; the number of the join-assembling holes is as same as that of the locating guide sleeves; a grouting passage is formed in the precast slab body; one end of the grouting passage is communicated with the bottoms of the join-assembling holes; and the other end of the grouting passage is open in the upper surface of the precast slab body. The easy-to-assemble floating track bed precast slab, provided by the invention, is mainly used for the construction of rail transit.
Owner:GERB QINGDAO VIBRATION CONTROL +1

Rail sleeper and ballast-free track structure

InactiveUS20050252985A1Facilitate rapid installationEasy to replaceBallastwayRail fastenersEngineeringMechanical engineering
According to one aspect of the invention there is provided a prefabricated rail sleeper [10] suitable for use in erecting a track structure [30]. The rail sleeper [10] comprises an elongate body portion [12] for supporting rails [14], the body portion [12] including a top surface [12,1], a bottom face [12.1] and at least two side faces [12.3], and terminating at least at one end thereof in a transition joint formation [16] dimensioned matingly to engage a complimentarily dimensioned transition joint formation [16] of an adjacent rail sleeper [10] in use so as to form a substantially continuous track structure. The sleeper [10] also includes a series of block formations [20], each of which is at least partially outwardly flared and extending beyond the side faces [12.3] of the body portion [12] so as to increase shear interlock of the sleeper [10] with the track bed to reduce longitudinal creep; as well as a series of transverse drainage ducts [26] extending underneath the rail sleeper [10] for allowing rainwater drainage between different side faces [12.3] of the body portion [12] and away from the rail sleeper. The invention extends to a ballast-free track structure [30] comprising at least two rail sleepers [10] according to the invention wherein the sleepers are located in spaced parallel orientation on a ballast-free track bed so as to define a centre drain [32] between the sleepers; and including a mesh [34] located between the sleepers [10] for reinforcing the centre drain [32].
Owner:HIGHFLYER INVESTMENTS & TRADING 6

Method for controlling cracks of double-block type ballastless track bed slabs

The invention discloses a method for controlling cracks of double-block type ballastless track bed slabs. The method includes steps of pouring concrete back and forth among double-block type sleepers according to 'Z'-shaped paths; vibrating the concrete, in other words, performing a secondary vibrating process in procedures for pouring the concrete of double-block type track bed slabs according to slump and the initial setting time of the concrete, performing press polish on plastered surfaces, performing rough screeding by the aid of wood float after the concrete is filled into forms, secondarily plastering the surfaces 2 hours after the concrete is filled into the forms, and performing tertiary press polish on the plastered surfaces 4 hours after the concrete is filled into the forms; loosening vertical screw adjusters, fish plates and fasteners, in other words, loosening vertical adjusting screws 4.5 hours after the concrete is plastered on the surfaces, loosening the corresponding fish plates from two sides of a pouring starting end, timely loosening the fasteners by the aid of a bolt fastening machine after bolts of the fish plates are loosened, and removing connection; spraying maintenance liquid. The cracks of the ballastless track bed slabs can be reduced in construction procedures, so that trains can assuredly run safely, economically and quickly. The method has the advantages of simplicity in process, convenience in operation and easiness in construction. Besides, the construction quality of the ballastless track bed slabs can be improved.
Owner:CHINA TIESIJU CIVIL ENG GRP CO LTD

Cyclic loading tamping teststand for indoor crushed stone ballast track beds

ActiveCN104198310AImplement cyclic loadingAchieving a tamping testUsing mechanical meansMaterial strength using repeated/pulsating forcesMarine engineeringTrackway
The invention relates to a cyclic loading tamping teststand for indoor crushed stone ballast track beds, and belongs to the technical field of railway engineering blast track bed detection. The cyclic loading tamping teststand comprises a cyclic loading apparatus, a tamping apparatus, a movable loading vehicle, a loading hydraulic system, a ballast track bed, a track panel, a ballast box I, a power supply, a ballast box II, a groundwork and ground pit system, a track bed detection system, a system damping apparatus and a vehicle walking track. The cyclic loading tamping teststand performs cyclic loading tests to simulate loading effect of a train on a ballast track bed and simulate tamping operation of the crushed stone ballast track bed, performs test analysis and test research on track bed compactness. The cyclic loading tamping teststand is capable of simulating operation of a train with the shaft weight of 0.5-35 ton and the speed per hour of 40-350 Km/h on a ballast track, performing real-time testing and monitoring and acquiring data. During tamping simulation operation, the cyclic loading tamping teststand is capable of realizing the tamping frequency variation scope of 15 Hz-60 Hz and realizing multi-station operation with high testing precision and high testing efficiency, satisfies indoor repeatability test demands, and is strong in anti-interference capability.
Owner:KUNMING UNIV OF SCI & TECH

Subway distributed vibration signal similarity determination method

ActiveCN110751108AEffective extraction of local location featuresSpatial distance measurement is convenientSubsonic/sonic/ultrasonic wave measurementCharacter and pattern recognitionPattern recognitionTest sample
The invention discloses a subway distributed vibration signal similarity determination method, which comprises the following steps: 1) collecting vibration response of structural parts including a track bed and a tunnel wall along a subway tunnel through an optical fiber sensor, and obtaining an original monitoring vibration data set; 2) carrying out signal preprocessing on the original monitoringvibration data set, and extracting a distributed vibration signal data set excited by a subway coming vehicle; 3) normalizing the distributed vibration signal data set, and dividing the normalized distributed vibration signal data set into a training sample subset and a test sample subset; 4) constructing an SDAE network model; training an SDAE model by using the training sample and the test sample; 5) selecting two groups of vibration signals, respectively inputting the signals into the SDAE model, and then extracting the feature representation of the last middle layer of the SDAE model to form two groups of feature matrixes. According to the method, the local position features contained in the signals are extracted, the vibration signal similarity is expressed through the spatial distance between the feature matrixes, and the method is simple and reliable.
Owner:WUHAN UNIV OF TECH

Existing railway reinforcement construction method in jacking process of box body

An existing railway reinforcement construction method in the jacking process of a box body comprises the following steps: performing grouting treatment to railway ballast below an existing railway positioned in a to-be-jacked area, moving concrete sleepers, penetrating wooden ties among the concrete sleepers, mounting locking tracks, forming a beam arranging ditch, penetrating a beam, mounting a longitudinal beam, and the like. The method provided by the invention has the following advantages: the operation of renewing concrete sleepers is reduced, so that the damage to the original road bed/track bed is reduced, and the stability of the road bed is high; the depth of a dug ditch and the work amount of reinforcement are reduced, the construction period and the on-line operation time are shortened, and the risk of personnel safety and running of an existing railway is lowered; grouting solidification can effectively reduce the problem that vibration is caused when a train passes, so that railway ballast rolls into the ditch, and then repeated operation can be avoided; insulating boards of 3 cm in thickness and H-steel of 45 cm in height are arranged at the lower part of a steel rail, so that the reserved space is enlarged, a treatment space is provided for the rising phenomenon that possibly occurs when the box body is jacked, and running safety of the existing railway can be ensured.
Owner:CHINA RAILWAY SIXTH GRP TIANJIN RAILWAY CONSTR +1

Modularized steel structure track bed with adjustable gauge

The invention relates to a modularized steel structure track bed with an adjustable gauge. The modularized steel structure track bed is formed by sequentially splicing by adopting a modularized structure, and adjacent modules are connected through a connecting plate by bolts; the modules comprise longitudinal groove steel frames and lateral groove steel frames, which are mutually connected vertically, wherein the longitudinal groove steel frames are arranged on both sides of each of tracks, a distance is regulated according to the gauge of the tracks, and the longitudinal groove steel frames are mounted on a track bed mounting base through basic connecting seats; the tracks are fixedly connected to the lateral groove steel frames. Compared with the prior art, the modularized steel structure track bed disclosed by the invention can determine the gauge according to specific application, then selects the tracks with the corresponding gauges and the track bed modules, the modules are sequentially connected together in the longitudinal direction through the connecting plate to form the required track length, and the basic connecting seats are connected with the track bed mounting bases or other devices through bolts in the vertical direction and the lateral direction so as to have the function of regulation; the modularized steel structure track bed is convenient to assemble and mount.
Owner:TONGJI UNIV

Steel spring floating slab monolithic track bed construction method based on track engineering

The invention discloses a steel spring floating slab monolithic track bed construction method based on track engineering, which comprises the following steps: S1, installing a walking rail in a tunnel, and pouring a support base body at the bottom of the tunnel; s2, manufacturing a floating slab reinforcement cage , arranging vibration isolator assemblies on the reinforcement cage at intervals, and fixing steel rails to the top of the reinforcement cage; s3, laying an isolation layer on the supporting base body, placing the floating slab reinforcement cage on the isolation layer and calibrated, and then conducting concrete pouring to form a ballast bed; and s4, after the ballast bed reaches the designed strength, lifting the ballast bed to the designed height through a vibration isolator assembly. According to the technical scheme, the beneficial effects are as follows: the reinforcement cage is manufactured in a prefabricated mode, ground operation with a larger operation space can beselected, large-batch manufacturing can be conducted at the same time, the operation efficiency can be improved, jacking can be conducted after ballast bed pouring is completed, a ballast bed has certain elasticity, impact force generated by vehicles can be absorbed in the operation process, and the service life of a rail is prolonged.
Owner:CHINA TIESIJU CIVIL ENG GRP CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products