Convenient and efficient construction method for piles
A construction method and high-efficiency technology, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of timeliness and work efficiency to be improved, and achieve the effect of saving waiting time for feeding materials, improving timeliness, and convenient construction.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0026] A convenient and efficient pile construction method comprises the following steps:
[0027] (1) Placement: place the immersed tube system of the equipment on the set pile position, or near the pile position that has been constructed, or in the center of the cement-soil pile position that has been constructed; pile shoes can be pre-embedded on the pile position ;
[0028] (2) Immersed tube: press the immersed tube system of the equipment to sink to the set depth;
[0029] (3) Pouring: lift up the internal ramming pipe system, pour the pile body or lower the prefabricated pile body;
[0030] (4) Pulling out the tube: pull out the outer tube, fill the gap around the prefabricated pile with filler and curing agent, and the pile is formed;
[0031] The immersed tube system in step (1) is a single-steel outer tube with a set rigidity, a single-steel inner rammed tube and a connecting device; the outer diameter of the inner rammed tube is smaller than the inner diameter of t...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com