A method for controlling overfilling concrete at the top of bored piles

A technology of bored piles and poured concrete, which is applied in the direction of sheet pile walls, buildings, and foundation structure engineering, can solve the problems of time-consuming and costly, and achieve the effects of shortening the construction period, saving costs, and improving economic benefits

Active Publication Date: 2017-12-15
浙江省地矿建设有限公司
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] In the construction of bored piles, the general design requires overfilling the length of 1.5-2.0D (D is the pile diameter of the bored pile) to ensure the quality of the concrete at the design pile top elevation, but in actual construction, due to the pile diameter Relatively small, the actual superfill height is far greater than this length. In this way, in the later excavation process of the foundation pit, it is necessary to remove the excess concrete above the design level, which is not only time-consuming, but also requires a lot of money.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A method for controlling overfilling concrete at the top of bored piles

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0023] The present invention will be further described below in conjunction with accompanying drawing of description, but protection scope of the present invention is not limited thereto:

[0024] A kind of method of controlling bored cast-in-place pile pile top superfilling concrete of the present invention, comprises the following steps:

[0025] 1) Construction of bored pile holes: construction of bored pile holes is carried out according to the design requirements;

[0026] 2) Concrete pouring: pour concrete into the drilled cast-in-place pile hole obtained in step 1), and pour the concrete above the design superfill height, the design superfill height is 1.5-2.0D or 500cm above the pile top, where D is the diameter of the bored pile;

[0027] 3) Concrete scouring: connect the top of the improved drill pipe to the drilling rig, extend the bottom of the drill pipe to the design pile top elevation of the bored pile, then turn on the mud pump connected to the drilling rig, a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a method for controlling excessively-poured concrete on the pile top of a cast-in-situ bored pile. The method for controlling excessively-poured concrete on the pile top of the cast-in-situ bored pile comprises the steps that a cast-in-situ bored pile hole is constructed, concrete is poured, and redundant concrete on the pile top is scoured, specifically, in-situ scouring of a drill rod is maintained, and then the drill rod is slowly lifted upwards while the edge is scoured; and finally, the drill rod is completely lifted upwards, and scouring is completed. According to the method for controlling excessively-poured concrete on the pile top of the cast-in-situ bored pile, high-speed slurry is sprayed out horizontally from outlets of connecting ribs and a slurry baffle through the improved drill rod, the excessively-poured concrete on the pile top of the cast-in-situ bored pile is scoured and diluted, and the height of the excessively-poured concrete on the pile top of the cast-in-situ bored pile is effectively controlled, so that the pile with the set pile height is obtained; the workload of chiseling away the redundant concrete on the pile top after a foundation pit is excavated in the later stage is avoided, the construction period is shortened, the cost is greatly reduced, and the economic benefits are improved.

Description

technical field [0001] The invention belongs to the technical field of building construction, and in particular relates to a construction method capable of controlling the height of superfilled concrete at the top of bored piles. Background technique [0002] Bored pile is the most common construction method used in building pile foundation construction. Its main function is to provide vertical load support for the building or use its friction with the soil around the pile to provide anti-buoyancy. [0003] In the construction of bored piles, the general design requires overfilling the length of 1.5-2.0D (D is the pile diameter of the bored pile) to ensure the quality of the concrete at the design pile top elevation, but in actual construction, due to the pile diameter Relatively small, the actual superfill height is far greater than this length. In this way, in the later excavation process of the foundation pit, it is necessary to remove the excess concrete above the design...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D5/34E02D15/04
CPCE02D5/34E02D15/04
Inventor 翁奔哲操海滨陈南桥何侃侃
Owner 浙江省地矿建设有限公司