A technology for existing lines and bridges, which is applied in the field of demolition of main beams of existing bridges on the upper span to achieve the effect of reducing management costs, reducing mechanical input costs, and reducing construction costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0061] Such as figure 1 A method for dismantling the main girder of a bridge spanning an existing line is shown. The main girder of the bridge to be removed is a main girder spanning the existing railway line. The multiple beam sections 14 to be removed have the same structure and are all reinforced concrete beam sections, and the beam sections 14 to be removed are assembled from M reinforced concrete T beams 15 from left to right, wherein M is positive Integer and M≥3; the front and rear ends of the beam section 14 to be removed are respectively supported on a supporting pier, and the bridge deck pavement layer is laid on the beam section 14 to be removed; for any one of the beam sections to be removed When carrying out the demolition construction of the whole group in section 14, the following steps are included:
[0062] Step 1, bridge deck pavement milling: milling the bridge deck pavement on the currently constructed beam section;
[0063] The currently constructed beam...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com