A cofferdam construction method
A construction method and technology for cofferdams, which are applied in infrastructure engineering, construction, etc., can solve problems such as water leakage and sealing of cofferdams, and achieve the effects of improving sealing performance, improving observation performance, and improving safety and stability.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment Construction
[0045] A kind of cofferdam construction method is described further below.
[0046] A cofferdam construction method, comprising the following steps:
[0047] S1. Pre-construction preparations: first conduct on-site surveys to understand the site environment, geology and underwater conditions, and then work out the locations of the cofferdams and diversion channels according to the drawings.
[0048] S2. Site cleaning: Draw the general layout of the construction and determine the excavation route, base elevation, slope slope and earthwork stacking location, and remove all obstacles, trees and weeds in the excavation area.
[0049] S3. Cofferdam setting-out: locate the cofferdam, and release the position from the beginning to the end of the cofferdam according to the layout plan, and measure the fill elevation with a spirit level during the filling process.
[0050] S4. Driving wooden piles: When purchasing wooden piles, choose high-quality wood. The wooden piles are 6 meters l...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com