A Load Restoration Method Considering the Cooling and Hot Start-up Interval of Units
A technology of load recovery and unit start-up, applied in the field of power grid, can solve the problems of increasing the time of load recovery, affecting the efficiency of network structure reconstruction, and not being directly applicable, so as to achieve the effect of increasing the amount of load recovery
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0096] Taking the IEEE10-machine 39-node system as an example, the power grid topology is as follows: image 3 As shown, unit 30 is a hydroelectric unit with self-starting capability, and the rest are thermal power units without self-starting capability. The start-up time of each branch road is set as 4min, and the load recovery of each step of grid reconfiguration is optimized by adopting the existing load recovery method and the method of the present invention respectively, and the load recovery amount is compared as Figure 4 shown.
[0097] Because the existing method starts the lines outside the recovery path when the load is restored, the load recovery time is increased, which in turn affects the start-up time of the remaining units to be restored, resulting in some units that could have been hot-started before they can be cold-started. With the existing method, all units are fully recovered in 236 minutes, while the method of the present invention is used to optimize t...