A determination method for main transformer capacity demand in power supply area based on substation load level
A technology of main transformer capacity and judgment method, which is applied to electrical components, circuit devices, AC network circuits, etc., and can solve problems such as lack of decision-making basis
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] A method for judging the capacity demand of a main transformer in a power supply area based on the load level of a substation, comprising the following steps:
[0023] (1) Obtain substation load m k , the configured number of main transformers in operation in the substation n k , the capacity of a single main transformer in the substation s i , to get the running status g(m k ,n k ), g(m k ,n k )=0, the operating state of the substation is no-load substation; g(m k ,n k )=1, the operating state of the substation is a substation with light load; g(m k ,n k ) = 2, the operating state of the substation is a substation with moderate load; g(m k ,n k ) = 3, the operating state of the substation is a substation with heavy load; g(m k ,n k ) = 4, the operating state of the substation is an overloaded substation;
[0024] (2) According to the operating state of the substation in the power supply area, the operating state y of the substation in the power supply area...