A drainage type municipal road and its construction method
A technology for municipal roads and roadbeds, applied in the directions of roads, roads, side ditches/curbs, etc., can solve problems such as the inability to ensure normal drainage of roads
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0023] Earthwork works first, and when there is filling on the top of the soil subgrade, it will be constructed at the same time as the pipeline project to reduce the amount of earthwork excavation, and then the pipeline project will be excavated, the foundation will be treated, the pipe will be lowered, the pipe foundation will be poured, and the inspection well will be built locally. Backfilling, closed water test, all backfilling, then construction of the road subbase, excavation after completion, construction of rainwater connection pipes, installation of curbs at the same time, then base construction, and finally pavement construction, sidewalk construction at the same time as base and pavement construction , Install flow meters and alarms and other equipment after the construction is completed.
Embodiment 2
[0025] In embodiment one, add following operation:
[0026] After the construction of the mixture is completed, it should be maintained in time to maintain a certain humidity. It should not be too dry or too wet. The curing period should not be less than 7 days, and it should be covered with geotextiles.
[0027] Earthwork works first, and when there is filling on the top of the soil subgrade, it will be constructed at the same time as the pipeline project to reduce the amount of earthwork excavation, and then the pipeline project will be excavated, the foundation will be treated, the pipe will be lowered, the pipe foundation will be poured, and the inspection well will be built locally. Backfilling, closed water test, all backfilling, then construction of the road subbase, excavation after completion, construction of rainwater connection pipes, installation of curbs at the same time, then base construction, and finally pavement construction, sidewalk construction at the same t...
Embodiment 3
[0029] In embodiment two, add following operation:
[0030] When rolling the subgrade, follow the principle of "light first and then heavy, first edge and then middle, first slow and then fast".
[0031] Earthwork works first, and when there is filling on the top of the soil subgrade, it will be constructed at the same time as the pipeline project to reduce the amount of earthwork excavation, and then the pipeline project will be excavated, the foundation will be treated, the pipe will be lowered, the pipe foundation will be poured, and the inspection well will be built locally. Backfilling, closed water test, all backfilling, then construction of the road subbase, excavation after completion, construction of rainwater connection pipes, installation of curbs at the same time, then base construction, and finally pavement construction, sidewalk construction at the same time as base and pavement construction , After the construction is completed, install flowmeters, alarms and ot...