BIM-based shield tunnel construction management system
A technology of tunnel construction and management system, applied in the field of electronic information, can solve problems such as the introduction of BIM technology, and achieve the effect of increasing portability and reusability, and increasing work efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0052] see figure 1 , the present invention discloses a BIM-based shield tunnel construction management system, the construction management system includes: several RFID tags 1, one or more RFID readers 2, one or more front-end operation terminals 3, background server4.
[0053] The RFID tag 1 is set on the tunnel segment to store the code information corresponding to the segment. The RFID reader 2 is used to write segment coding information into the RFID tag 1 , and can also read the segment coding information from the RFID tag 1 . The RFID reader-writer 2 can also be used as a part of the front-end operation terminal 3 , but the RFID reader-writer 2 can be set separately from the main part of the front-end operation terminal 3 .
[0054] Both the front-end operation terminal 3 and the back-end server 4 are loaded with a BIM model system 5 and a construction inspection system 6 . The front-end operation terminal 3 is connected to the RFID reader-writer 2 to control the RFI...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com