Water quenching process revising method of shaft under different configuration densities
A technology of arrangement density and water quenching, which is applied in the field of quenching and cooling technology, can solve problems such as shaft parts and interface heat transfer coefficient changes, and achieve the effect of avoiding water quenching cracking and reducing product performance fluctuations
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0027] Water quenching of an alloy steel piece, the size of the alloy steel piece: Ф80*5000 (mm), adopts horizontal heating and horizontal quenching and cooling. The clamping method is: place 8 shafts horizontally, and the distance between the centers of each two shafts is 160mm; place 5 layers up and down, and the distance between the centers of each two layers is 160mm; through tests, it is concluded that the product performance that meets the requirements can be obtained when a single shaft is immersed in water for 240s. It is required to revise the quenching and cooling process under the current clamping method.
[0028] According to the numerical simulation method, the correction coefficient is 1.25, and the calculation formula for the water quenching time after correction is: t 修正 =K*t 标准 According to calculations, the immersion time of this clamping method should be 300s, and the alloy steel parts are cooled by immersion according to this time, so as to obtain product ...
Embodiment 2
[0030] An alloy steel piece is quenched by water-air alternate quenching and cooling process, the quenching medium is water and air, the size of the alloy steel piece: Ф150*5000 (mm), adopts horizontal heating and horizontal quenching and cooling. The clamping method is: place 6 pieces horizontally, and the center distance between each two pieces is 300mm; place 4 layers up and down, and the center distance between every two layers is 300mm. It is required to give the revised water-air alternate quenching and cooling process.
[0031] Methods as below:
[0032] (1) Determine the water-air alternate quenching and cooling process for a single shaft, that is, the first water cooling 120s + air cooling 150s + the second water cooling 180s + air cooling 200s + the third water cooling 150s;
[0033] (2) The revised water quenching time calculation formula: t 修正 =K*t 标准
[0034] In the formula: t 修正 is the corrected water quenching time; K is the correction coefficient; t 标准 is...
Embodiment 3
[0039] A certain alloy steel part is quenched by polymer water-soluble medium. The size of the alloy steel part: Ф80*5000 (mm), adopts vertical heating and vertical quenching cooling. The clamping method is: hoist 20 shafts around the center according to the distance between the centers of every two shafts of 200mm. Through the test, it can be concluded that when a single shaft is immersed in the polymer water-soluble medium for 360s, the required product performance can be obtained. It is required to revise the quenching and cooling process under the current clamping method.
[0040] According to the numerical simulation method, the correction coefficient is 1.20, and the calculation formula for the water quenching time after correction is: t 修正 =K*t 标准 According to the calculation, the immersion time of the clamping method in the polymer-based water-soluble medium should be 432s. According to this time, the alloy steel parts are immersed in the polymer-based water-soluble ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com