The construction method of the sales office structure first up and then down

A technology of first up, then down, construction method, applied in the direction of building structure, construction, etc., can solve the problem of not being able to meet the node requirements of the owner's sales office, and achieve the effect of flexible operation

Active Publication Date: 2016-09-14
SHANGHAI CONSTR NO 5 GRP CO LTD
View PDF5 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, in view of the demand that the superstructure of some projects needs to be completed and put into use ahead of schedule, especially the sales department, the existing conventional practice cannot meet the node requirements for the advance development of the owner's sales office, so there is an urgent need for an upper The construction method of the structure such as the owner's sales office is first constructed and put into use, and then the underground structure is constructed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • The construction method of the sales office structure first up and then down
  • The construction method of the sales office structure first up and then down

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] In order to make the above objects, features and advantages of the present invention more comprehensible, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0022] like figure 1 and 2 As shown, the present invention provides a construction method of the sales office structure first up and then down, including:

[0023] Step S1, first constructing the column pile 1 on the construction site, then grading and excavating to a preset depth on all sides of the construction site and supporting a short bent frame 2 in the excavated space, and pouring on the short bent frame 2 is completed basement roof 3;

[0024] Step S2, carry out layer-by-layer construction of the above-ground structure and subsequent fine decoration on the basement roof 3, so that the sales office and other buildings can be put into use in advance;

[0025] Step S3, remove the short bent frame 2, excavate an excavation...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a method for constructing an upper structure of a sales office at first and then constructing a lower structure of the sales office. The method comprises the following steps of arranging piles on a construction site; digging space with preset depth on four slopes of the construction site and propping up short bent frames in the dug space; pouring a basement roof on the short bent frames; and constructing different layers of a ground structure on the basement roof and performing follow-up refined decoration; detaching the short bent frames; digging a soil discharging ramp from one side of the construction site; digging a soil discharging road which is connected with the soil discharging ramp in the middle of the side, which is provided with the soil discharging ramp, in the construction site; symmetrically digging earthwork between the basement roof and a basement bottom plate on two sides of the soil discharging road in the construction site; conveying the earthwork out of the construction site through the soil discharging road and the soil discharging ramp; and performing follow-up construction of a basement structure. By the method, the upper structure of the building can be finished at first and can be used as soon as possible, and the problem that the construction period is short but the upper structure is required to be used ahead of time is solved.

Description

technical field [0001] The invention relates to a construction method of a sales office structure that goes up first and then down. Background technique [0002] In the building construction of the prior art, usually the basement structure is first completed and then the upper structure is constructed, and then the decoration construction is carried out. However, in view of the demand that the superstructure of some projects needs to be completed and put into use ahead of schedule, especially the sales department, the existing conventional practice cannot meet the node requirements for the advance development of the owner's sales office, so there is an urgent need for an upper Structures such as the construction method of the owner's sales office are first constructed and put into use, and then the underground structure is constructed. Contents of the invention [0003] The purpose of the present invention is to provide a construction method of the sales office structure ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E04B1/35
Inventor 章曾平方怡王水良
Owner SHANGHAI CONSTR NO 5 GRP CO LTD