A technology for concrete face and face rockfill dams, applied in dams, barrages, weirs, etc., can solve the problems of increased leakage, increased deflection and deformation of panels, and crushed panels of panels, so as to reduce maintenance costs and reduce costs. The effect of small panel length, shortened time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0026] The technical solution of the present invention is further described below in conjunction with the accompanying drawings, but the scope of protection is not limited to the description.
[0027] Such as figure 1 , figure 2 , image 3 As shown, a foundation concrete face rockfill dam according to the present invention includes a face rockfill dam 2, a face plate 3, a cushion area 4 and a transition area a5, and the transition area a5, the cushion area 4 and the face plate 3 Covering the facing water surface of the CFRD 2 successively, a base 1 is provided under the CFRD 2, and a transition zone b6 is provided between the base 1 and the CFRD 2 as a filling transition material.
[0028] The base 1 includes a base anti-seepage area 8 on the upstream side and a base bearing area 7 on the downstream side. The height of the base 1 is less than 100m, and the base bearing area 7 can be made of normal concrete, roller compacted concrete, cemented sand and gravel, One or more ...