Tool change construction method for soil reinforcement from the outside of the soil bin by the earth pressure balance shield machine in the sand layer

A technology of earth pressure balance and construction method, which is applied to earth drilling, mining equipment, tunnels, etc. It can solve problems such as easy blockage of grouting openings, unreinforced ground, and equipment damage, so as to reduce construction workload and shorten construction time , strong safety effect

Active Publication Date: 2018-06-29
CHINA RAILWAY 16 BUREAU GRP BEIJING METRO ENG CONSTR +2
View PDF7 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] Aiming at the defects in the prior art, the object of the present invention is to provide a tool-changing construction method in which the earth pressure balance shield machine in the sand layer reinforces the soil body from the outside of the soil bin, which overcomes the inability of the ground to be reinforced and the sand layer in the prior art. Poor gas holding capacity, easy blockage of grouting port, unclear grouting construction method, equipment damage caused by hardened cement mortar, large workload of chiseling hardened cement mortar, difficulty in advanced grouting reinforcement construction and other shortcomings and deficiencies. Safe tool change construction of earth pressure balance shield machine in sand layer

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Tool change construction method for soil reinforcement from the outside of the soil bin by the earth pressure balance shield machine in the sand layer
  • Tool change construction method for soil reinforcement from the outside of the soil bin by the earth pressure balance shield machine in the sand layer
  • Tool change construction method for soil reinforcement from the outside of the soil bin by the earth pressure balance shield machine in the sand layer

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] The present invention will be described in detail below in conjunction with specific embodiments. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention. These all belong to the protection scope of the present invention.

[0037] Such as Figure 1-Figure 3 As shown, this embodiment provides an earth pressure balance shield machine in the sand layer to reinforce the soil from the outside of the soil bin to fill the bin and change the construction method, that is, the front reinforcement of the cutter head, which is used in a tunnel in Guangzhou; the bottom of the shield machine cutter head The depth is 14m underground, and the ground above the stop position is an intersection. In order to prevent the structure of the...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

PropertyMeasurementUnit
thicknessaaaaaaaaaa
thicknessaaaaaaaaaa
thicknessaaaaaaaaaa
Login to View More

Abstract

The invention provides a tool changing construction method realizing soil mass reinforcement from outside of a soil room for an earth pressure balance shield machine in a sand layer. The construction method comprises the following steps: step 1, cement slurry is poured to the front of a cutterhead and is poured into the soil room to replace muck; step 2, accelerator slurry is poured into the cement slurry outside the soil room; step 3, the soil room is cleaned, and a tool is changed; step 4, tunneling is recovered. Difficult advanced grouting construction operation and construction operation for removing hardened cement slurry through boring are avoided, damage to equipment due to the hardened cement slurry is eliminated, a grouting construction operation mode is determined clearly, and the construction operation amount is reduced effectively; the tool changing construction method has the advantages of short construction time, high efficiency and high safety.

Description

technical field [0001] The invention relates to a construction method in the technical field of tunnel engineering, in particular to a construction method for an earth pressure balance shield machine in a sand layer to reinforce the soil body and change tools from the outside of the soil bin. Background technique [0002] With the improvement of my country's urbanization level, a large number of intercity railways, high-speed railways, and urban rail transit constructions need to be carried out, including many tunnel projects. A large number of tunnels need to be constructed using the shield method. The earth pressure balance shield method is a fully mechanical construction method commonly used in shield tunneling construction. It uses an earth pressure balance shield machine to cut the soil through the cutter head in front of the shield machine and pass the muck through the screw conveyor. After being transported out of the tunnel, the shield machine is pushed forward unde...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D9/08
CPCE21D9/08
Inventor 郭银波高宪民周阳宗李晓亮武铁路赵守宪朱小藻沈水龙范志高苏周勃肖瑞传刘锐孙国辉韩守初刘方吴怀娜
Owner CHINA RAILWAY 16 BUREAU GRP BEIJING METRO ENG CONSTR