Control device and method used for jacking construction of ultra-long horizontal pipe curtain and based on inclination measurement
A control device and horizontal pipe technology, applied in vertical shaft equipment, earthwork drilling, wellbore lining, etc., can solve problems such as failure of jacking, long jacking distance, wasted construction period, etc., and achieve the effect of real-time monitoring and adjustment to ensure accuracy
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0030] The present invention will be further explained below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the following specific embodiments are only used to illustrate the present invention and are not intended to limit the scope of the present invention. It should be noted that the words "front", "rear", "left", "right", "upper" and "lower" used in the following description refer to the directions in the drawings, and the words "inner" and "outer ” refer to directions towards or away from the geometric center of a particular part, respectively.
[0031] Such as figure 1 As shown, a kind of inclinometer-based ultra-long horizontal pipe curtain jacking construction control device and method according to the present invention includes: a jacking system 1, which is used to provide horizontal jacking force during the pipe curtain construction process; a test system 2. It is used for real-time monitoring of the axis deviatio...