Steel bridge deck structure capable of being changed into be permanent structure from temporary structure
A temporary structure and permanent technology, applied in the direction of bridges, bridge parts, bridge materials, etc., can solve the problems that cannot be converted into permanent structures, and achieve the effect of shortening the construction period and workload
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach
[0018] The steel bridge deck structure that can be temporarily converted to permanent of the present invention, its preferred embodiment is:
[0019] The temporary structure of the bridge deck structure includes a base 1 and a support block 2, both of which are welded by steel plates to form a hollow structure, and the support block 2 is welded on the upper surface of the base 1, and each support block 2 is welded with two A screw rod 3 for installing a rail fastener, and concrete pouring holes 4 are respectively reserved on the base 1 and the support block 2;
[0020] After the concrete 14 is poured into the base 1 and the support block 2 through the concrete pouring hole 4, the bridge deck structure is converted from a temporary structure to a permanent structure.
[0021] The base 1 and the supporting block 2 are arranged with transverse stiffeners 5 and longitudinal stiffeners 6 respectively, and holes are left in the transverse stiffeners 5 and longitudinal stiffeners 6 ....
specific Embodiment
[0035] 1. Temporary deck structure stage
[0036] During the construction of the steel girder structure, the L-shaped steel plate 7 is pre-welded on the surface of the beam structure 12. After the construction of the beam structure 12 is completed, the bridge deck structure 13 is hoisted on the beam structure 12 by a crane, and the bridge deck structure 13 Use the L-shaped steel plate 7 to align it in place during hoisting. After the bridge deck structure 13 is in place, connect the beam structure 12 and the bridge deck structure 13 through the L-shaped steel plate 7, and finally install steel rails on the support blocks to form a temporary bridge deck structure. meet the conditions of access.
[0037] 2. Permanent bridge deck structure stage
[0038] In the construction stage of the permanent bridge, the existing temporary bridge deck structure is converted into a permanent bridge deck structure. Firstly, the bridge deck structure 13 and the beam structure 12 are welded into...