Embodiment 1
[0124] Such as figure 1 As shown, a heuristic power distribution network black start reconstruction method based on tabu search includes the following steps:
[0125] Step 1. Input the original data, including the DG, load, and line parameters of the distribution network to be optimized. For the load, the load type and unit power failure loss are also required;
[0126] Step 2. Determine the relevant parameters of the optimization model based on engineering experience and actual needs, the time period for restoration and reconstruction, the number of lines that are allowed to be put into operation at the same time, the system reserve ratio, the load fluctuation coefficient, and the maximum frequency deviation allowed by the system;
[0127] Step 3. Establish a distribution network black start reconstruction model;
[0128] S31. Clarify the black start reconstruction model of the distribution network: assume that the distribution network is completely out of power, and the ext...