Fixing device and fixing method for submarine cable with four layers of armored steel wires
A technology of armored steel wire and fixing device, which is used in cable installation, ground cable installation, etc., can solve the problems of low tensile strength, long screw bending, complicated installation, etc., to improve stability, improve tensile strength, safety, etc. Excellent performance
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0024] Embodiment 1: A fixing device for a submarine cable 1 with four layers of armored steel wire 10, comprising: a submarine cable 1, one end of the submarine cable 1 has four layers of armored steel wire 10 and a submarine cable core 11, which is peeled off from the submarine cable core 11 A fixing ring 12 is respectively arranged on at least two layers of armored steel wires 10, and the armored steel wires 10 are fixed by bending and clamping the fixing rings 12 inwardly or outwardly, and the fixed armored steel wires 10 are rounded platform bodies; 2. One end of the fixed main body 2 is provided with an installation hole 20 connected to the outside and a cable through hole 21; the fixed main body 2 is provided with an inner cavity 22 with a rounded table, the inner cavity 22 communicates with the cable through hole 21, and one end of the sea cable 1 is placed inside In the cavity 22, the other end of the fixed main body 2 is provided with a fixed plate 23 with a glue fill...
Embodiment 2
[0026] Embodiment 2: The difference between this embodiment and the foregoing embodiments is that the armored steel wire 10 is fixed by three fixing rings 12, specifically as figure 2As shown, the submarine cable 1 has a first layer of armored steel wire 100, a second layer of armored steel wire 101, a third layer of armored steel wire 102 and a fourth layer of armored steel wire 103, and the second layer of armored steel wire 101 is provided with a first A fixed ring 120, the second layer of armored steel wire 101 and the first layer of armored steel wire 100 are bent outward together to clamp the first fixed ring 120 and cling to the third layer of armored steel wire 102; the third layer of armored steel wire 102 A second fixing ring 121 is arranged on the top, and the third layer of armored steel wire 102 is bent inward to clamp the second fixing ring 121. The third layer of armored steel wire 103 is provided with a third fixing ring 122, and the fourth layer of armored ste...
Embodiment 3
[0027] Embodiment Three: The difference between this embodiment and the foregoing embodiments is that the armored steel wire 10 is fixed by four fixing rings 12, specifically as image 3 As shown, the submarine cable 1 has a first layer of armored steel wire 100, a second layer of armored steel wire 101, a third layer of armored steel wire 102 and a fourth layer of armored steel wire 103, and the second layer of armored steel wire 101 is provided with a first A fixed ring 120, the second layer of armored steel wire 101 is bent outwards to clamp the first fixed ring 120 and is close to the third layer of armored steel wire 102; the first layer of armored steel wire 100 is provided with a second fixed ring 121, The first layer of armored steel wire 100 is bent outwards to clamp the second fixed ring 121 and is close to the third layer of armored steel wire 102; the third layer of armored steel wire 102 is provided with a third fixed ring 122, and the third layer of armored wire 1...
PUM
Login to View More Abstract
Description
Claims
Application Information