Deep foundation pit floury soil stratum deep-well well point rainfall construction method and application

A technology of well point dewatering and construction methods, applied in infrastructure engineering, construction, etc., can solve the problems of foundation pits that cannot be dug deep, construction obstacles, mud and quicksand, etc., to improve soil stability, prevent excessive settlement, The effect of preventing longitudinal landslide

Inactive Publication Date: 2019-11-08
XINJIANG COMM CONSTR GRP
View PDF0 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] During the construction of the traffic road, if the geology of the silty clay stratum is encountered, due to its poor stability, in the excavation project of the deep foundation pit of the subway station, in order to dry the soil in the excavation range of the foundation pit groundwater, and reduce the head height of the lower confined aquifer to ensure the stability of the foundation pit during construction. Traditional drainage methods can no longer meet the requirements of construction
If the dewatering construction cannot be done in time, there will be serious phenomenon of mud turning, mud and quicksand, which will not only make the foundation pit unable to dig deep, but also cause a large amount of water and soil loss, causing the slope to become unstable or the nearby ground to collapse. It will also affect the safety of nearby buildings
[0003] In view of the specific geological conditions of the silty clay stratum, when construction is carried out on the silty soil, due to the difficulty of water seepage in the silty soil stratum, light well points are usually used for dewatering during construction. One light well point to achieve multi-point synchronous dewatering, but if you want to meet the preset dewatering requirements, you need to set up many light well points, and the layout of light well points is scattered, which will greatly hinder the construction in the pit. At the same time, when the number of light well points is too large, it is necessary to set up a pump for each light well point and observe the pumping situation of each light well point, which will undoubtedly increase the equipment cost and labor cost

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Deep foundation pit floury soil stratum deep-well well point rainfall construction method and application
  • Deep foundation pit floury soil stratum deep-well well point rainfall construction method and application
  • Deep foundation pit floury soil stratum deep-well well point rainfall construction method and application

Examples

Experimental program
Comparison scheme
Effect test

Embodiment

[0062] The present application provides a construction method for deep well point dewatering in silty soil formations of deep foundation pits, which is especially suitable for silty clay formations.

[0063] This application specifically takes Pingchuan Road Station of Phase I Project of Urumqi Rail Transit Line 2 as a typical example for illustration. see figure 1 and figure 2 , The geology of Pingchuan Road Station of Urumqi Rail Transit Line 2 Phase I Project is mainly silty clay stratum with poor stability. According to the geological survey report, there are confined water and phreatic water in the stratum, and the distribution of aquifers is discontinuous. The diving is mainly buried in silt, with a gravel content of about 15%, and up to 20% locally. The roof is buried at a depth of 1.2-4m and a thickness of about 14-17m. The buried depth of the water level is 3-5m, the stable water level elevation is 854.6-856.1m, and the converted water inflow is 454.102m 3 / d, med...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
Spacingaaaaaaaaaa
Depthaaaaaaaaaa
Diameteraaaaaaaaaa
Login to view more

Abstract

The embodiment of the invention provides a deep foundation pit floury soil stratum deep-well well point rainfall construction method and application, and relates to the field of traffic building and construction. The construction method comprises the steps of drilling a plurality of out-of-pit precipitation wells outside a foundation pit, and drilling a plurality of in-pit precipitation wells in the foundation pit; and lowering a plurality of well pipes to the corresponding out-of-pit precipitation wells and the corresponding in-pit precipitation wells to form corresponding in-pit well pipes and out-of-pit well pipes. By means of the deep foundation pit floury soil stratum deep-well well point rainfall construction method and the application, the out-of-pit precipitation wells and the in-pit precipitation wells are combined for precipitation, and the conditions that when light well points cannot meet the precipitation requirement, the number of the light well points are gradually increased, consequently the number of the well points is increased, and the excavation amount is increased are effectively avoided; and in-pit precipitation and out-of-pit precipitation are combined, the groundwater in soil within the foundation pit excavation scope is effectively drained, and construction work of construction machinery and workers in the pit are facilitated.

Description

technical field [0001] The invention relates to the field of traffic construction and construction, in particular to a construction method for dewatering a deep well point in a powdery soil layer of a deep foundation pit and an application thereof. Background technique [0002] During the construction of the traffic road, if the geology of the silty clay stratum is encountered, due to its poor stability, in the excavation project of the deep foundation pit of the subway station, in order to dry the soil in the excavation range of the foundation pit Groundwater, as well as reducing the head height of the lower confined aquifer, ensure the stability of the foundation pit during construction. Traditional drainage methods can no longer meet the requirements of construction. If the dewatering construction cannot be done in time, there will be serious phenomenon of mud turning, mud and quicksand, which will not only make the foundation pit unable to dig deep, but also cause a larg...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D19/10
CPCE02D19/10
Inventor 高凯凯高书义冯超强陈芳努尔麦麦提·阿卜力米提蒲荣泽刘博马峥杨秋菊
Owner XINJIANG COMM CONSTR GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products