A Temporary Fastening Connection System Applicable to Prefabricated Large Components

A technology for fastening connections and prefabricated components, applied in building components, structural elements, building reinforcements, etc., can solve the problems of increasing labor costs and energy consumption, inconvenient operation, and large amount of steel, and simplify prestressing tension. The effect of work, easy operation and cost reduction

Active Publication Date: 2022-04-26
UNIV OF SCI & TECH BEIJING
View PDF12 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In order to disperse the excessive compressive stress at the anchorage end of prestressed steel bars, the existing temporary fastening system often needs to be equipped with additional steel pressure-bearing backing plates, which increases the cost
In order to avoid the setting of backing plates, in some applications, large and long end anchors are used to disperse the stress and ensure the stability during tension; the existing method not only uses a lot of steel, but also is heavy, inconvenient to operate, and increases manpower Cost and Energy Consumption

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A Temporary Fastening Connection System Applicable to Prefabricated Large Components
  • A Temporary Fastening Connection System Applicable to Prefabricated Large Components
  • A Temporary Fastening Connection System Applicable to Prefabricated Large Components

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0037] Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited by the embodiments set forth herein. Rather, these embodiments are provided for more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.

[0038] Such as Figure 1 to Figure 15 As shown, this implementation stereoscopically provides a temporary fastening connection system that can be used for prefabricated large components, including large prefabricated components 1, and the fastened connection system includes anchor beams 5, which are located on the two ends of large prefabricated components 1 and the positions are corresponding Anchor beams 5 form a group, and there...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a temporary fastening connection system applicable to prefabricated large components, including large prefabricated components, the fastening connection system includes anchor beams, anchor beams located at both ends of large prefabricated components and corresponding in positions form a group, the anchor beams There are multiple groups symmetrically arranged, and each group of anchor beams is installed with prestressed tendons on the inside and outside of the large prefabricated component; Suspension studs are installed at both ends, and the suspension studs are vertically arranged with the prestressed tendons and pass through the middle of the anchor beam; after the fastening connection systems are installed on the two large prefabricated components, the two large prefabricated components are connected , the prestressed tendons are prestressed after passing through the anchor beams on the two large prefabricated components. The fastening connection system can be suspended and installed at any set height, effectively avoiding the setting of prestressed tunnels or tensioning tooth plates on the original concrete components, and can be reused with low cost.

Description

technical field [0001] The invention relates to the technical field of temporary fastening of prefabricated large components, in particular to a temporary fastening connection system applicable to prefabricated large components. Background technique [0002] In the construction, installation, and testing of civil engineering structures, it is often necessary to temporarily fasten some large prefabricated components, and tensioned prestressed steel bars are a widely used temporary fastening measure. [0003] At present, the prestressed steel bars used for temporary fastening of prefabricated large components often penetrate into the channels reserved in the prefabricated concrete components. Under the state of tension and anchorage, the precompressive stress is transmitted to the end face of the concrete component through the anchorage and its lower backing plate; Some use templates to make tooth plates during prefabrication of concrete components, and anchor prestressed stee...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E02D29/045E02D29/16E04C5/08
CPCE02D29/045E02D29/16E02D29/10E04C5/08
Inventor 张举兵时一鸣李松林张凯伦胡志强柴晓鑫卞正涛