[0036] Examples see Figure 1-9 As shown, the installation method of the two-way prestressed cable is as follows:
[0037] Step 1, erecting the assembly platform 1 of the assembled steel truss 19, the short slideway 9 and the cable support system;
[0038] Step 2: After the three steel trusses are assembled on the assembly platform, slide the first steel truss out of the overhang from the assembly platform 1 to the short slideway 9, and lay the cable end of the transverse prestressed cable 14 along the horizontal direction The channel is drawn to the cast steel node 21 of the first steel truss, and the cable end of the transverse prestressed cable 14 is fixedly connected to the cast steel node 21;
[0039] Step 3: After the fifth steel truss is assembled, slide the third steel truss out of the assembly platform to the cantilever of the short slideway 9, and fix the connection under each cast steel node 21 of the third steel truss Steel struts 22, cable clamp nodes 23 and tra...
PUM