Construction method for shield entry under complicated working conditions
A technology with complex working conditions and construction methods, applied in underground chambers, earthwork drilling, wellbore lining and other directions, can solve problems such as complex construction conditions and achieve the effect of ensuring safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] The present invention will be further described below with reference to the drawings and embodiments.
[0030] The construction method of shield tunneling under complicated working conditions of the present invention:
[0031] 1. To ensure the smooth entry of the shield into the tunnel and the safety of surrounding buildings and underground pipelines, the entrance of the tunnel shall be reinforced with soil. Such as figure 1 As shown in 2, the soil reinforcement of the shield tunnel entrance gate adopts triple-pipe high pressure jet grouting pile construction (to reduce the impact on the surrounding environment), and the design pile diameter of a row of piles near the ground wall 7 in the shield tunnel entrance reinforcement area is 800mm , The design pile diameter of other parts is 1200mm, adopts plum-shaped arrangement, adjacent piles overlap 300mm. The entrance reinforcement will be implemented in conjunction with the reinforcement of the bottom of the air shaft foundati...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com