Backfill compaction method in narrow area of foundation pit
A technology for foundation pits and areas, applied in infrastructure engineering, soil protection, construction, etc., can solve problems such as outdoor floor cracking, damage, deformation of underground pipelines, etc., to achieve easy quality assurance, control of backfill quality, layer thickness increased effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment
[0048] Example, the foundation pit of a housing construction project in Shenzhen is backfilled. The perimeter of the foundation pit of the project is 240m, the backfill depth is 9.0m, and the width of the backfill surface, that is, the distance between the foundation pit enclosure structure and the basement exterior wall is 1.2m. The design compaction degree of foundation pit backfill shall not be less than 94%. It was originally planned to use cohesive soil as the backfill material, and mechanical compaction or tamping was used as the backfill process. Because the backfill area is narrow, the original backfill plan cannot be implemented, so it is decided to adopt the method of the present invention.
[0049] The backfill areas on the east, south and west sides of the foundation pit shall be backfilled with stone powder slag, and the north side shall be made of recycled construction waste materials, and the backfill material shall be loosely spread to a thickness of 1.5m. Sto...